Developer + Project Manager

Use this pathway when you own the development decision and also coordinate construction delivery. It does not duplicate the two disciplines: it shows where one decision changes the other and what record is needed before moving forward.

Decision gatesConstruction consequencesEvidence-led controlCost + programme alignmentLast reviewed 11 August 2026

Learn the development decision

Property Development

Understand strategy, site, feasibility, acquisition, planning, finance, sales and settlement before integrating delivery controls.

Open resource

Learn the delivery discipline

Construction Project Management

Understand design, consent, procurement, site, quality, commercial, inspection and close-out controls.

Open resource

Apply both roles

Open the project workspace

Connect decisions, tasks, evidence, drawings, RFIs, cost, programme and close-out in one project record.

Open resource

Integrated lifecycle

Decision → consequence → control → evidence → next decision

Open each gate when a development decision is about to create a design, construction, commercial or programme commitment.

  1. 1 · OpportunityIs this site and strategy worth investigating?

    Construction consequence

    Likely yield, access, services, hazards and existing conditions shape design and construction complexity.

    Project-management action

    Run a first-pass screen, record assumptions and commission only the investigations needed to reach the next gate.

    Required evidence

    Site screen, title/plan references, map layers, comparable-sales basis and risk notes.

    Cost effect

    Set investigation allowances and an early construction/civil range without treating either as a quote.

    Programme effect

    Set the offer and due-diligence decision dates before commissioning reports.

    Consent effect

    Screen likely planning/building/authority pathways without assuming an approval outcome.

    Procurement effect

    Commission only proportionate early investigations; do not appoint construction scope from a desktop screen.

    Next PM action / decision

    Decide whether to reject, monitor, negotiate or proceed to pre-offer feasibility.

  2. 2 · AcquisitionWhat must be verified before an offer condition is waived?

    Construction consequence

    Title, planning, ground, infrastructure and existing-building issues can change buildable area, method and sequence.

    Project-management action

    Coordinate lawyer, planner, surveyor, engineers, building reviewer, QS/accountant and lender around one due-diligence matrix.

    Required evidence

    Current title/instruments, LIM/property file, planning memo, inspections, service checks, finance/tax advice and feasibility version.

    Cost effect

    Update land value, civil/build allowances, professional fees, finance, contingency and exit assumptions.

    Programme effect

    Track condition deadlines, report lead times, approvals and settlement dependencies.

    Consent effect

    Identify approvals, conditions and investigations that affect the protected acquisition decision.

    Procurement effect

    Obtain focused fee proposals and early cost evidence needed for due diligence; keep unverified build allowances separate.

    Next PM action / decision

    Proceed, renegotiate, extend conditions or exit—and record why.

  3. 3 · Concept and yieldWhich concept balances market, planning, buildability and return?

    Construction consequence

    Form, levels, structure, retaining, access, services and product choices determine construction risk and cost.

    Project-management action

    Run coordinated design reviews and constructability checks before the layout becomes expensive to change.

    Required evidence

    Option drawings, planning advice, survey/geotech/civil inputs, QS estimate, market feedback and decision register.

    Cost effect

    Compare options using one scope basis and show unverified allowances separately.

    Programme effect

    Identify design freezes, long-lead investigations and approval-critical decisions.

    Consent effect

    Compare option compliance risk and supporting-report needs before freezing yield.

    Procurement effect

    Test constructability, material/system availability and cost-plan scope before selecting the concept.

    Next PM action / decision

    Select a controlled concept and brief the consent/design team.

  4. 4 · Approvals and designIs the project sufficiently coordinated to lodge and later build?

    Construction consequence

    Gaps between architecture, structure, civil, services, H1, products and consent conditions become RFIs, variations and delay on site.

    Project-management action

    Maintain design responsibility, drawing, RFI, consent-condition, producer-statement and authority registers.

    Required evidence

    Current issue sets, coordination records, calculations, specifications, lodgement receipts, RFIs and approved changes.

    Cost effect

    Update feasibility at each material design or consent change and before procurement.

    Programme effect

    Track information release, authority response, consultant dependencies and long-lead procurement dates.

    Consent effect

    Coordinate the application, consent conditions, design evidence and authorised-change pathway.

    Procurement effect

    Release only controlled scope; connect submittal, long-lead and design-responsibility dates to approval status.

    Next PM action / decision

    Confirm the approved scope and pre-construction readiness gate.

  5. 5 · Procurement and mobilisationWho is appointed, for exactly what scope, price, time and evidence?

    Construction consequence

    Missing scope, exclusions, unconfirmed products and unclear hold points become construction claims and quality gaps.

    Project-management action

    Package work, issue common information, level returns and link appointment, insurance, competency, programme and close-out obligations.

    Required evidence

    RFQ issue, quote comparison, clarifications, approvals, PO/subcontract, insurance and delivery/lead-time commitments.

    Cost effect

    Move approved commitments into the live forecast; never treat an unaccepted quote as committed cost.

    Programme effect

    Connect approvals, submittals, manufacture, delivery and site release dates.

    Consent effect

    Confirm the procured scope matches the current consent and pre-start obligations.

    Procurement effect

    Level scope, exclusions, approvals, insurance, lead time, evidence and close-out deliverables before award.

    Next PM action / decision

    Authorise mobilisation only when possession, safety, access, documents and hold points are ready.

  6. 6 · Construction controlCan the next work package proceed, be covered or be paid?

    Construction consequence

    Site quality, safety, sequencing and evidence determine rework, inspections, claims, CCC and buyer outcomes.

    Project-management action

    Use daily reports, lookahead, RFIs, variations, inspections, evidence requests, drawing revisions and ball-in-court controls.

    Required evidence

    Location-specific photos, approved documents, trade QA, consultant/council records, dockets, tests and formal decisions.

    Cost effect

    Reconcile instructed scope, commitments, claims, approved variations, forecast and contingency.

    Programme effect

    Track constraints, hold points, critical dependencies, recovery actions and evidence before concealment.

    Consent effect

    Use inspections, RFIs and authorised changes; never treat site progress as consent acceptance.

    Procurement effect

    Keep changes, deliveries, trade evidence and forecast commitments tied to the controlled scope.

    Next PM action / decision

    Release only verified work and keep the development forecast aligned with the site forecast.

  7. 7 · Completion and exitIs the project ready for practical completion, CCC, handover, sale or retention?

    Construction consequence

    Missing records, defects, commissioning and consent-condition evidence delay use, settlement, funding and buyer confidence.

    Project-management action

    Run defect, commissioning, CCC, warranty, as-built, handover and settlement readiness as linked close-out gates.

    Required evidence

    Inspection history, RBW records, producer statements, electrical/gas records, as-builts, manuals, warranties and accepted close-outs.

    Cost effect

    Forecast completion, retentions, unresolved variations, defect exposure, selling/settlement cost and remaining contingency.

    Programme effect

    Integrate final inspections, rectification, authority responses, title/sales, lender and settlement dates.

    Consent effect

    Track CCC, subdivision/title, consent conditions and authority acceptance as separate evidence states.

    Procurement effect

    Close trade defects, certification, as-builts, warranties and final accounts before representing the package complete.

    Next PM action / decision

    Close the project record, capture lessons and track post-completion obligations.

Use this in my project

Turn developer + project manager pathway into controlled action

Open the relevant workspace register, create the project-specific record, link the controlling documents and preserve evidence. The guide does not automatically approve or verify the action.

Open workspace