Procurement planning and commercial control

Auckland residential development Quote Register

Use this register to identify consultant fees, investigations, authority costs, utility charges, enabling works, civil packages, building trades, finishes, and close-out costs that may need a quote, estimate, allowance, or formal fee proposal.

Quote packages

182

Project stages

9

Storage

This browser only

Commercial warning

A quote register does not prove that scope is complete or that a supplier is suitable. Issue the current documents, compare quotes on the same basis, resolve exclusions and provisional sums, check authority charges directly, and obtain QS, legal, tax, insurance, lending, and contract advice where needed. Any “including GST” display below uses 15% only as a visible calculation assumption; confirm actual GST treatment with your accountant.

182 packages match the current filters

QR-001

High

Professional / report

Property, legal and feasibility

Record of Title and title instrument review

Obtain a written price or fee proposal for record of title and title instrument review.

Scope to be priced

Price the complete project-specific scope for record of title and title instrument review, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-002

High

Professional / report

Property, legal and feasibility

Sale and purchase agreement legal review

Obtain a written price or fee proposal for sale and purchase agreement legal review.

Scope to be priced

Price the complete project-specific scope for sale and purchase agreement legal review, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-003

High

Professional / report

Property, legal and feasibility

LIM report

Obtain a written price or fee proposal for lim report.

Scope to be priced

Price the complete project-specific scope for lim report, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-004

High

Professional / report

Property, legal and feasibility

Auckland Council property file

Obtain a written price or fee proposal for auckland council property file.

Scope to be priced

Price the complete project-specific scope for auckland council property file, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-005

High

Professional / report

Property, legal and feasibility

Planning desktop review

Obtain a written price or fee proposal for planning desktop review.

Scope to be priced

Price the complete project-specific scope for planning desktop review, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-006

High

Professional / report

Property, legal and feasibility

Planning pre-application advice

Obtain a written price or fee proposal for planning pre-application advice.

Scope to be priced

Price the complete project-specific scope for planning pre-application advice, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-007

High

Professional / report

Property, legal and feasibility

Site feasibility report

Obtain a written price or fee proposal for site feasibility report.

Scope to be priced

Price the complete project-specific scope for site feasibility report, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-008

High

Professional / report

Property, legal and feasibility

Market appraisal

Obtain a written price or fee proposal for market appraisal.

Scope to be priced

Price the complete project-specific scope for market appraisal, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-009

High

Professional / report

Property, legal and feasibility

Rental appraisal

Obtain a written price or fee proposal for rental appraisal.

Scope to be priced

Price the complete project-specific scope for rental appraisal, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-010

High

Professional / report

Property, legal and feasibility

Completed-development sales appraisal

Obtain a written price or fee proposal for completed-development sales appraisal.

Scope to be priced

Price the complete project-specific scope for completed-development sales appraisal, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-011

High

Professional / report

Property, legal and feasibility

Registered valuation

Obtain a written price or fee proposal for registered valuation.

Scope to be priced

Price the complete project-specific scope for registered valuation, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-012

High

Professional / report

Property, legal and feasibility

Development feasibility review

Obtain a written price or fee proposal for development feasibility review.

Scope to be priced

Price the complete project-specific scope for development feasibility review, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-013

High

Professional / report

Property, legal and feasibility

Accountant and tax advice

Obtain a written price or fee proposal for accountant and tax advice.

Scope to be priced

Price the complete project-specific scope for accountant and tax advice, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-014

High

Professional / report

Property, legal and feasibility

GST advice

Obtain a written price or fee proposal for gst advice.

Scope to be priced

Price the complete project-specific scope for gst advice, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-015

High

Professional / report

Property, legal and feasibility

Finance broker services

Obtain a written price or fee proposal for finance broker services.

Scope to be priced

Price the complete project-specific scope for finance broker services, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-016

High

Professional / report

Property, legal and feasibility

Lender establishment, valuation, monitoring, and drawdown fees

Obtain a written price or fee proposal for lender establishment, valuation, monitoring, and drawdown fees.

Scope to be priced

Price the complete project-specific scope for lender establishment, valuation, monitoring, and drawdown fees, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-017

High

Professional / report

Property, legal and feasibility

Quantity surveyor feasibility cost estimate

Obtain a written price or fee proposal for quantity surveyor feasibility cost estimate.

Scope to be priced

Price the complete project-specific scope for quantity surveyor feasibility cost estimate, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-018

High

Professional / report

Property, legal and feasibility

Independent due diligence consultant review

Obtain a written price or fee proposal for independent due diligence consultant review.

Scope to be priced

Price the complete project-specific scope for independent due diligence consultant review, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-019

High

Investigation / survey

Survey and investigations

Topographical survey

Obtain a written price or fee proposal for topographical survey.

Scope to be priced

Price the complete project-specific scope for topographical survey, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-020

High

Investigation / survey

Survey and investigations

Boundary redefinition survey

Obtain a written price or fee proposal for boundary redefinition survey.

Scope to be priced

Price the complete project-specific scope for boundary redefinition survey, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-021

High

Investigation / survey

Survey and investigations

Existing building measured survey

Obtain a written price or fee proposal for existing building measured survey.

Scope to be priced

Price the complete project-specific scope for existing building measured survey, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-022

High

Investigation / survey

Survey and investigations

Geotechnical desktop review

Obtain a written price or fee proposal for geotechnical desktop review.

Scope to be priced

Price the complete project-specific scope for geotechnical desktop review, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-023

High

Investigation / survey

Survey and investigations

Geotechnical site investigation

Obtain a written price or fee proposal for geotechnical site investigation.

Scope to be priced

Price the complete project-specific scope for geotechnical site investigation, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-024

High

Investigation / survey

Survey and investigations

Soil testing

Obtain a written price or fee proposal for soil testing.

Scope to be priced

Price the complete project-specific scope for soil testing, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-025

High

Investigation / survey

Survey and investigations

Contamination preliminary site investigation

Obtain a written price or fee proposal for contamination preliminary site investigation.

Scope to be priced

Price the complete project-specific scope for contamination preliminary site investigation, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-026

High

Investigation / survey

Survey and investigations

Detailed site investigation for contamination where advised

Obtain a written price or fee proposal for detailed site investigation for contamination where advised.

Scope to be priced

Price the complete project-specific scope for detailed site investigation for contamination where advised, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-027

High

Investigation / survey

Survey and investigations

Asbestos survey

Obtain a written price or fee proposal for asbestos survey.

Scope to be priced

Price the complete project-specific scope for asbestos survey, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-028

High

Investigation / survey

Survey and investigations

Arborist report

Obtain a written price or fee proposal for arborist report.

Scope to be priced

Price the complete project-specific scope for arborist report, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-029

High

Investigation / survey

Survey and investigations

Flood assessment

Obtain a written price or fee proposal for flood assessment.

Scope to be priced

Price the complete project-specific scope for flood assessment, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-030

High

Investigation / survey

Survey and investigations

Overland flow path assessment

Obtain a written price or fee proposal for overland flow path assessment.

Scope to be priced

Price the complete project-specific scope for overland flow path assessment, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-031

High

Investigation / survey

Survey and investigations

Stormwater feasibility

Obtain a written price or fee proposal for stormwater feasibility.

Scope to be priced

Price the complete project-specific scope for stormwater feasibility, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-032

High

Investigation / survey

Survey and investigations

Wastewater feasibility

Obtain a written price or fee proposal for wastewater feasibility.

Scope to be priced

Price the complete project-specific scope for wastewater feasibility, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-033

High

Investigation / survey

Survey and investigations

CCTV survey of stormwater network

Obtain a written price or fee proposal for cctv survey of stormwater network.

Scope to be priced

Price the complete project-specific scope for cctv survey of stormwater network, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-034

High

Investigation / survey

Survey and investigations

CCTV survey of wastewater network

Obtain a written price or fee proposal for cctv survey of wastewater network.

Scope to be priced

Price the complete project-specific scope for cctv survey of wastewater network, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-035

High

Investigation / survey

Survey and investigations

Underground service location

Obtain a written price or fee proposal for underground service location.

Scope to be priced

Price the complete project-specific scope for underground service location, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-036

High

Investigation / survey

Survey and investigations

Ground penetrating radar scanning

Obtain a written price or fee proposal for ground penetrating radar scanning.

Scope to be priced

Price the complete project-specific scope for ground penetrating radar scanning, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-037

High

Investigation / survey

Survey and investigations

Vacuum potholing

Obtain a written price or fee proposal for vacuum potholing.

Scope to be priced

Price the complete project-specific scope for vacuum potholing, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-038

High

Investigation / survey

Survey and investigations

Neighbouring property condition survey

Obtain a written price or fee proposal for neighbouring property condition survey.

Scope to be priced

Price the complete project-specific scope for neighbouring property condition survey, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-039

High

Consultant

Design and consent consultants

Planner

Obtain a written price or fee proposal for planner.

Scope to be priced

Price the complete project-specific scope for planner, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-040

High

Consultant

Design and consent consultants

Architect

Obtain a written price or fee proposal for architect.

Scope to be priced

Price the complete project-specific scope for architect, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-041

High

Consultant

Design and consent consultants

Architectural designer

Obtain a written price or fee proposal for architectural designer.

Scope to be priced

Price the complete project-specific scope for architectural designer, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-042

High

Consultant

Design and consent consultants

Structural engineer

Obtain a written price or fee proposal for structural engineer.

Scope to be priced

Price the complete project-specific scope for structural engineer, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-043

High

Consultant

Design and consent consultants

Civil engineer

Obtain a written price or fee proposal for civil engineer.

Scope to be priced

Price the complete project-specific scope for civil engineer, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-044

High

Consultant

Design and consent consultants

Geotechnical engineer

Obtain a written price or fee proposal for geotechnical engineer.

Scope to be priced

Price the complete project-specific scope for geotechnical engineer, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-045

High

Consultant

Design and consent consultants

Fire engineer where required

Obtain a written price or fee proposal for fire engineer where required.

Scope to be priced

Price the complete project-specific scope for fire engineer where required, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-046

High

Consultant

Design and consent consultants

Traffic engineer where required

Obtain a written price or fee proposal for traffic engineer where required.

Scope to be priced

Price the complete project-specific scope for traffic engineer where required, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-047

High

Consultant

Design and consent consultants

Acoustic consultant where required

Obtain a written price or fee proposal for acoustic consultant where required.

Scope to be priced

Price the complete project-specific scope for acoustic consultant where required, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-048

High

Consultant

Design and consent consultants

Hydraulic or drainage designer

Obtain a written price or fee proposal for hydraulic or drainage designer.

Scope to be priced

Price the complete project-specific scope for hydraulic or drainage designer, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-049

High

Consultant

Design and consent consultants

H1 energy assessor

Obtain a written price or fee proposal for h1 energy assessor.

Scope to be priced

Price the complete project-specific scope for h1 energy assessor, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-050

High

Consultant

Design and consent consultants

Quantity surveyor

Obtain a written price or fee proposal for quantity surveyor.

Scope to be priced

Price the complete project-specific scope for quantity surveyor, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-051

High

Consultant

Design and consent consultants

Landscape designer

Obtain a written price or fee proposal for landscape designer.

Scope to be priced

Price the complete project-specific scope for landscape designer, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-052

High

Consultant

Design and consent consultants

Resource consent application preparation

Obtain a written price or fee proposal for resource consent application preparation.

Scope to be priced

Price the complete project-specific scope for resource consent application preparation, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-053

High

Consultant

Design and consent consultants

Building consent application preparation

Obtain a written price or fee proposal for building consent application preparation.

Scope to be priced

Price the complete project-specific scope for building consent application preparation, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-054

High

Consultant

Design and consent consultants

Engineering approval application

Obtain a written price or fee proposal for engineering approval application.

Scope to be priced

Price the complete project-specific scope for engineering approval application, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-055

High

Consultant

Design and consent consultants

Consent RFI response allowances

Obtain a written price or fee proposal for consent rfi response allowances.

Scope to be priced

Price the complete project-specific scope for consent rfi response allowances, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-056

High

Consultant

Design and consent consultants

Producer statement preparation

Obtain a written price or fee proposal for producer statement preparation.

Scope to be priced

Price the complete project-specific scope for producer statement preparation, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-057

High

Consultant

Design and consent consultants

Construction monitoring

Obtain a written price or fee proposal for construction monitoring.

Scope to be priced

Price the complete project-specific scope for construction monitoring, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Required site visits, document review, meetings, calculations/report, drawings or schedules, consent/RFI input, revisions allowed, programme, deliverables, file formats, and professional sign-off where applicable.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Developer / development manager / project manager

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

2

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-058

High

Authority / utility

Council and authority costs

Resource consent deposit and processing fees

Obtain a written price or fee proposal for resource consent deposit and processing fees.

Scope to be priced

Price the complete project-specific scope for resource consent deposit and processing fees, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-059

Normal

Authority / utility

Council and authority costs

Building consent fees

Obtain a written price or fee proposal for building consent fees.

Scope to be priced

Price the complete project-specific scope for building consent fees, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-060

Normal

Authority / utility

Council and authority costs

Building and resource consent inspection or monitoring fees

Obtain a written price or fee proposal for building and resource consent inspection or monitoring fees.

Scope to be priced

Price the complete project-specific scope for building and resource consent inspection or monitoring fees, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-061

Normal

Authority / utility

Council and authority costs

Development contributions estimate

Obtain a written price or fee proposal for development contributions estimate.

Scope to be priced

Price the complete project-specific scope for development contributions estimate, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-062

Normal

Authority / utility

Council and authority costs

Engineering approval fees

Obtain a written price or fee proposal for engineering approval fees.

Scope to be priced

Price the complete project-specific scope for engineering approval fees, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-063

Normal

Authority / utility

Council and authority costs

Vehicle crossing approval fees

Obtain a written price or fee proposal for vehicle crossing approval fees.

Scope to be priced

Price the complete project-specific scope for vehicle crossing approval fees, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-064

Normal

Authority / utility

Council and authority costs

Corridor access request costs where relevant

Obtain a written price or fee proposal for corridor access request costs where relevant.

Scope to be priced

Price the complete project-specific scope for corridor access request costs where relevant, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-065

Normal

Authority / utility

Council and authority costs

Watercare connection or approval costs

Obtain a written price or fee proposal for watercare connection or approval costs.

Scope to be priced

Price the complete project-specific scope for watercare connection or approval costs, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-066

Normal

Authority / utility

Council and authority costs

Electricity connection or disconnection

Obtain a written price or fee proposal for electricity connection or disconnection.

Scope to be priced

Price the complete project-specific scope for electricity connection or disconnection, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-067

Normal

Authority / utility

Council and authority costs

Fibre or telecommunications relocation

Obtain a written price or fee proposal for fibre or telecommunications relocation.

Scope to be priced

Price the complete project-specific scope for fibre or telecommunications relocation, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-068

Normal

Authority / utility

Council and authority costs

Gas disconnection or relocation where relevant

Obtain a written price or fee proposal for gas disconnection or relocation where relevant.

Scope to be priced

Price the complete project-specific scope for gas disconnection or relocation where relevant, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-069

High

Authority / utility

Council and authority costs

Public drainage works approval and connection

Obtain a written price or fee proposal for public drainage works approval and connection.

Scope to be priced

Price the complete project-specific scope for public drainage works approval and connection, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-070

Normal

Authority / utility

Council and authority costs

Public stormwater or wastewater approvals

Obtain a written price or fee proposal for public stormwater or wastewater approvals.

Scope to be priced

Price the complete project-specific scope for public stormwater or wastewater approvals, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-071

Normal

Authority / utility

Council and authority costs

Temporary traffic management where relevant

Obtain a written price or fee proposal for temporary traffic management where relevant.

Scope to be priced

Price the complete project-specific scope for temporary traffic management where relevant, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current site address/legal details, proposal description, relevant plans, consent references, correspondence, application information, and utility or council forms requested by the authority.

Evidence / credentials required

Keep the official fee estimate, invoice basis, application reference, payment receipt, conditions, expiry, and named authority contact.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before the related application, approval, connection, inspection, or programme commitment.

Minimum competitive quotes

1

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-072

Normal

Trade / hire

Enabling works and site setup

Temporary fencing

Obtain a written price or fee proposal for temporary fencing.

Scope to be priced

Price the complete project-specific scope for temporary fencing, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-073

Normal

Trade / hire

Enabling works and site setup

Site safety and information signage

Obtain a written price or fee proposal for site safety and information signage.

Scope to be priced

Price the complete project-specific scope for site safety and information signage, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-074

Normal

Trade / hire

Enabling works and site setup

Site toilet and servicing

Obtain a written price or fee proposal for site toilet and servicing.

Scope to be priced

Price the complete project-specific scope for site toilet and servicing, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-075

Normal

Trade / hire

Enabling works and site setup

Site office or secure storage

Obtain a written price or fee proposal for site office or secure storage.

Scope to be priced

Price the complete project-specific scope for site office or secure storage, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-076

Normal

Trade / hire

Enabling works and site setup

Temporary power

Obtain a written price or fee proposal for temporary power.

Scope to be priced

Price the complete project-specific scope for temporary power, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-077

Normal

Trade / hire

Enabling works and site setup

Temporary water

Obtain a written price or fee proposal for temporary water.

Scope to be priced

Price the complete project-specific scope for temporary water, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-078

Normal

Trade / hire

Enabling works and site setup

Service disconnections

Obtain a written price or fee proposal for service disconnections.

Scope to be priced

Price the complete project-specific scope for service disconnections, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-079

Normal

Trade / hire

Enabling works and site setup

Demolition

Obtain a written price or fee proposal for demolition.

Scope to be priced

Price the complete project-specific scope for demolition, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.

QR-080

Normal

Trade / hire

Enabling works and site setup

Asbestos removal

Obtain a written price or fee proposal for asbestos removal.

Scope to be priced

Price the complete project-specific scope for asbestos removal, including labour, materials, plant, design input, coordination, delivery, testing, temporary works, protection, waste, documentation, and close-out items that apply. Require the supplier to identify anything not priced.

Key inclusions

Set-out, labour, materials, fixings, plant, access, handling, protection, testing, cleaning, waste, warranties, as-builts, certificates, producer statements, Records of Work, and return visits that apply.

Selected incl. 15%: Not entered

Variance: Not entered

Open full RFQ planning and commercial fields

Clarifications and exclusions to resolve

Resolve GST, exclusions, assumptions, provisional sums, quantities, design responsibility, access, working hours, lead time, escalation, price validity, variations, testing, inspections, warranties, defects, retention, payment terms, and interfaces with other packages.

Documents to issue with RFQ

Issue the current drawing register, relevant architectural/engineering/civil plans, specifications, schedules, reports, consent conditions, programme, site information, scope sheet, quality requirements, and contract terms. Mark preliminary information clearly.

Evidence / credentials required

Check legal business name, NZBN where relevant, insurance, licences or LBP status where relevant, competent-person evidence, H&S information, references, capacity, proposed personnel, programme, product data, and exclusions.

Applicability

Project-specific — confirm whether this package applies before requesting pricing.

Responsible person

Construction project manager / quantity surveyor

Required before

Before budget approval, contractor appointment, purchase order, subcontract, or start of the related work.

Minimum competitive quotes

3

Source / Where to verify

Verify scope against the current project brief, Record of Title, LIM/property file, Auckland Unitary Plan and consent documents, architectural/engineering/civil drawings, specifications, authority requirements, contract, programme, site conditions, consultant advice, and manufacturer instructions. Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, or project contract.