Site management termsAll stages
Site diary
A chronological written record of daily site events, decisions, labour, weather, delays, and instructions.
Where it is used
Used every construction day as project evidence.
Example sentence
The site diary noted heavy rain stopped excavation at 11:30.
Related trade
Construction manager
Site management termsAll stages
Daily report
A structured daily site record covering progress, people, weather, inspections, photos, delays, safety, and tomorrow's plan.
Where it is used
Used as the main day-to-day project record.
Example sentence
Attach photos before the waterproofing was covered to today's daily report.
Related trade
Construction manager
Programme termsAll stages
Lookahead programme
A short-range plan, usually one to three weeks, showing immediate work, blockers, inspections, deliveries, and trade sequencing.
Where it is used
Used in site coordination and subcontractor planning.
Example sentence
The two-week lookahead shows cladding cannot start until cavity inspection passes.
Related trade
Construction manager
Programme termsProgramme
Critical path
The sequence of tasks that directly controls the project finish date.
Where it is used
Used when deciding which delays matter most.
Example sentence
The roofing delay is on the critical path because linings cannot start until the building is dry.
Related trade
Project manager
Quality termsAll stages
RFI
Request for Information: a formal question when drawings, specifications, or site conditions are unclear.
Where it is used
Used before making assumptions or changing work.
Example sentence
Raise an RFI for the roof-wall flashing conflict.
Related trade
Construction manager
Contract termsAll stages
Site instruction
A written instruction issued under the project communication/contract process.
Where it is used
Used when directing a trade or recording a decision.
Example sentence
The site instruction told the roofer to stop until the revised flashing detail was issued.
Related trade
Project manager
Contract termsContract administration
Variation
A change to scope, cost, time, selection, or method compared with the agreed contract.
Where it is used
Used when work differs from the original agreement.
Example sentence
The client upgrade to timber flooring is a variation.
Related trade
Project manager
Handover termsPractical completion
Practical completion
The contract point where work is sufficiently complete for use/handover, subject to the contract wording and agreed outstanding items.
Where it is used
Used near handover.
Example sentence
Do not issue practical completion until critical documents and safety items are complete.
Related trade
Project manager
Handover termsPost-construction
DLP
Defects liability period or maintenance period: the post-handover period where defects are reported, tracked, and repaired according to the contract.
Where it is used
Used after handover.
Example sentence
The sticking door was added to the DLP defect log.
Related trade
Construction manager
Council inspection termsCode Compliance Certificate
CCC
Code Compliance Certificate: council/BCA statement that, on reasonable grounds, the completed work complies with the issued building consent.
Where it is used
Used at project closeout.
Example sentence
The CCC application needs inspection records and producer statements.
Related compliance source
Auckland Council building consents: Auckland Council explains local building consent processes, CCC, related certificates, producer statements, LBP notification, and whether resource consent may also be needed.
Building consent termsConsent review
Building consent
Council/BCA approval of plans and specifications for proposed building work.
Where it is used
Used before consented work starts.
Example sentence
Build exactly to the building consent unless a minor variation or amendment is approved.
Related trade
Designer / builder / council
Related compliance source
MBIE Build to the consent: MBIE guidance explains that work should be built to the issued building consent, inspections must be managed, and records/certificates should be kept for CCC.
Building consent termsPre-construction
Resource consent
Planning approval that may be needed for land use, density, height, earthworks, trees, stormwater, or other Auckland planning matters.
Where it is used
Used before or alongside building consent where triggered.
Example sentence
The planner confirmed whether the addition needs resource consent.
Related compliance source
Auckland Council building consents: Auckland Council explains local building consent processes, CCC, related certificates, producer statements, LBP notification, and whether resource consent may also be needed.
Building consent termsAll stages
Minor variation
A small change to consented work that council may approve without a full amendment, depending on the circumstances.
Where it is used
Used when site work changes from the consent.
Example sentence
Ask council whether the drainage route change is a minor variation or amendment.
Related trade
Builder / council
Related compliance source
MBIE Making changes to plans: Use when a site change may require a minor variation or amendment before work continues.
Building consent termsAll stages
Amendment
A formal change to a building consent, usually needed when a change is more than minor.
Where it is used
Used when design or compliance changes affect the consent.
Example sentence
The structural beam change needs an amendment before work continues.
Related trade
Designer / council
Related compliance source
MBIE Making changes to plans: Use when a site change may require a minor variation or amendment before work continues.
Building consent termsCloseout
LBP
Licensed Building Practitioner: a licensed person who carries out or supervises restricted building work.
Where it is used
Used for restricted building work records and council requirements.
Example sentence
Collect the LBP Record of Work before CCC.
Related trade
LBP / builder
Related compliance source
Auckland Council building consents: Auckland Council explains local building consent processes, CCC, related certificates, producer statements, LBP notification, and whether resource consent may also be needed.
Council inspection termsCCC
Record of Work
A document completed by an LBP for restricted building work they carried out or supervised.
Where it is used
Used for CCC/handover records.
Example sentence
The roofer and carpenter Records of Work are on the CCC tracker.
Related compliance source
MBIE Build to the consent: MBIE guidance explains that work should be built to the issued building consent, inspections must be managed, and records/certificates should be kept for CCC.
Council inspection termsCloseout
Producer Statement PS3
A construction/installation statement often used to support council compliance assessment for specific work.
Where it is used
Used where consent or council requires it.
Example sentence
The waterproofing PS3 is needed before CCC submission.
Related trade
Installer / specialist
Related compliance source
Auckland Council building consents: Auckland Council explains local building consent processes, CCC, related certificates, producer statements, LBP notification, and whether resource consent may also be needed.
Council inspection termsCloseout
Producer Statement PS4
A construction review statement often issued by an engineer or professional who reviewed work.
Where it is used
Used where consent or council requires it.
Example sentence
The engineer's PS4 is required after retaining wall construction review.
Related compliance source
Auckland Council building consents: Auckland Council explains local building consent processes, CCC, related certificates, producer statements, LBP notification, and whether resource consent may also be needed.
Building consent termsStructure
B1 Structure
Building Code clause covering structural performance.
Where it is used
Used for foundations, framing, bracing, retaining, beams, lintels, and fixings.
Example sentence
Check B1 and the engineer drawings before accepting that beam change.
Related trade
Engineer / builder
Related compliance source
NZ Building Code B1 Structure: Check structure requirements, B1/AS1, Verification Methods, structural engineer design, bracing, foundations, wind, earthquake, and consented structural drawings.
Building consent termsAll stages
B2 Durability
Building Code clause covering durability of building elements.
Where it is used
Used for timber treatment, cladding, fixings, coatings, and product suitability.
Example sentence
The coastal fixing substitution must be checked for B2 durability.
Related trade
Builder / supplier
Related compliance source
NZ Building Code B2 Durability: Check durability expectations for materials and systems, alongside manufacturer literature and consented specifications.
Building consent termsDrainage/external
E1 Surface water
Building Code clause covering surface water disposal and protection from water entering buildings.
Where it is used
Used for stormwater, gutters, downpipes, site falls, and drainage.
Example sentence
The driveway fall must not direct water toward the garage.
Related trade
Drainlayer / civil contractor
Related compliance source
NZ Building Code E1 Surface water: Check stormwater, surface water, drainage paths, and council/engineer stormwater design.
Building consent termsEnvelope
E2 External moisture
Building Code clause covering keeping external moisture from causing dampness or damage.
Where it is used
Used for cladding, roofing, windows, doors, flashings, decks, and penetrations.
Example sentence
The window head flashing is an E2-critical detail.
Related trade
Cladder / roofer
Related compliance source
NZ Building Code E2 External moisture: Check E2/AS1, consented wall/roof details, cladding specifications, flashing details, and manufacturer installation requirements.
Building consent termsWet areas
E3 Internal moisture
Building Code clause covering wet areas, surfaces, and moisture inside the building.
Where it is used
Used for bathrooms, laundries, waterproofing, surfaces, and ventilation.
Example sentence
Check E3 and the waterproofing manual before tiling starts.
Related trade
Waterproofer / tiler
Related compliance source
NZ Building Code E3 Internal moisture: Check wet-area surfaces, ventilation, waterproofing details, and manufacturer systems against consented documents.
Building consent termsExterior works
F4 Safety from falling
Building Code clause covering permanent safety from falling, such as barriers and some stairs/decks.
Where it is used
Used for decks, stairs, barriers, retaining drops, and openings.
Example sentence
The deck barrier detail needs F4 verification.
Related compliance source
NZ Building Code F4 Safety from falling: Check barriers, stairs, decks, retaining drops, fall risks, consented details, and inspection requirements.
Building consent termsPlumbing
G12 Water supplies
Building Code clause covering safe water supply.
Where it is used
Used for plumbing, hot water, pipework, and water supply systems.
Example sentence
The hot water system must follow G12 and the manufacturer's manual.
Related compliance source
NZ Building Code G12 Water supplies: Check hot/cold water supply requirements, plumber producer statements/certificates where applicable, and consented plumbing layouts.
Building consent termsInsulation
H1 Energy efficiency
Building Code clause covering energy efficiency and the thermal envelope.
Where it is used
Used for insulation, glazing, slab edge/floor/wall/roof systems, and energy calculations.
Example sentence
The window substitution must be checked against H1 documentation.
Related trade
Designer / builder
Related compliance source
NZ Building Code H1 Energy efficiency: Check insulation, glazing, thermal envelope, energy calculations, and consented H1 documentation.
Framing termsFoundations/framing
NZS 3604
New Zealand timber-framed building standard used where a residential building is within its scope.
Where it is used
Used for many low-rise timber-framed residential projects.
Example sentence
Check whether the engineer has used NZS 3604 or specific design.
Related trade
Builder / engineer
Related compliance source
NZS 3604 Timber-framed buildings: Use where the project is within NZS 3604 scope; always confirm against the consented structural drawings and engineer details.
Cladding termsEnvelope
E2/AS1
Acceptable Solution for some external moisture details when the project and products are within its scope.
Where it is used
Used for many roof, cladding, window, and flashing details.
Example sentence
Do not assume E2/AS1 applies without checking the consented details.
Related trade
Designer / cladder
Related compliance source
NZ Building Code E2 External moisture: Check E2/AS1, consented wall/roof details, cladding specifications, flashing details, and manufacturer installation requirements.
Site management termsEarthworks
BeforeUdig
Service location request system used before excavation to help identify underground services.
Where it is used
Used before digging, trenching, drilling, or piling.
Example sentence
BeforeUdig records were checked before the drainage trench was opened.
Related trade
Earthworks contractor
Site management termsSite establishment
TMP
Traffic Management Plan, used when work affects roads, footpaths, berms, or public traffic/pedestrians.
Where it is used
Used around deliveries, skips, cranes, or works in the road corridor.
Example sentence
The skip on the road needs corridor/TMP confirmation.
Related trade
Traffic contractor
Foundation termsSet-out
Set-out
Marking the building, levels, boundaries, and work positions on site.
Where it is used
Used before earthworks, foundations, drainage, and framing.
Example sentence
Surveyor set-out confirmed the finished floor level.
Related trade
Surveyor / builder
Foundation termsSet-out
Datum
A fixed reference level used to set heights on site.
Where it is used
Used for foundations, drainage, floors, and exterior levels.
Example sentence
Do not move the datum peg until final levels are checked.
Related trade
Surveyor / builder
Foundation termsConcrete slabs
DPM
Damp-proof membrane, usually a sheet membrane under concrete slabs where specified.
Where it is used
Used before slab pours.
Example sentence
The DPM was taped around penetrations before mesh went down.
Related trade
Builder / concrete contractor
Foundation termsConcrete slabs
Reinforcing mesh
Welded steel mesh used in concrete where specified.
Where it is used
Used in slabs and concrete elements.
Example sentence
The mesh must be supported before the pour.
Related trade
Concrete contractor
Foundation termsFoundations
Rebar
Steel reinforcing bar used in concrete footings, beams, pads, or walls.
Where it is used
Used in foundations and structural concrete.
Example sentence
Photograph rebar before concrete is poured.
Foundation termsSubfloor
Pile
Vertical support element used to transfer load to ground.
Where it is used
Used for raised floors, decks, or engineered foundations.
Example sentence
The pile positions must match the pile plan.
Related trade
Builder / piling contractor
Foundation termsSubfloor
Bearer
Horizontal member supported by piles and supporting floor joists.
Where it is used
Used in subfloor framing.
Example sentence
Check bearer treatment and fixings before floor sheets.
Framing termsSubfloor
Joist
Horizontal member supporting floor sheets, ceilings, or decking.
Where it is used
Used in floors and decks.
Example sentence
Services should not cut joists without approved detail.
Framing termsWall framing
Stud
Vertical wall framing member.
Where it is used
Used in timber wall frames.
Example sentence
The stud layout must suit linings and services.
Related trade
Builder/framer
Framing termsWall framing
Nog
Short horizontal timber blocking between studs.
Where it is used
Used for stiffening and fixing support.
Example sentence
Add nogs for bathroom accessories before lining.
Related trade
Builder/framer
Framing termsWall framing
Lintel
Structural member over an opening.
Where it is used
Used over windows, doors, and large openings.
Example sentence
The lintel schedule controls the required lintel.
Related trade
Builder/framer
Framing termsFraming
Bracing
Structural resistance to wind and earthquake loads.
Where it is used
Used in walls, subfloor, and roof systems.
Example sentence
Do not let services cut bracing elements without approval.
Related trade
Builder / engineer
Framing termsFraming
Hold-down
Fixing or connector that resists uplift or bracing forces.
Where it is used
Used at bracing walls, roof tie-downs, and foundations.
Example sentence
The bracing hold-down must be installed before inspection.
Related trade
Builder/framer
Roofing termsRoof framing
Truss
Prefabricated roof frame member.
Where it is used
Used to form roof structure.
Example sentence
Do not cut a truss unless the truss designer approves it.
Related trade
Builder / truss supplier
Roofing termsRoof framing
Rafter
Sloping roof framing member.
Where it is used
Used in conventionally framed roofs.
Example sentence
Rafters must match the structural detail.
Related trade
Builder/framer
Roofing termsRoof framing
Purlin
Roof support member for roof cladding.
Where it is used
Used under metal roofing or roof cladding systems.
Example sentence
Check purlin spacing against the roofing manual.
Related trade
Roofer / builder
Roofing termsRoofing
Roof underlay
Underlay installed beneath roof cladding.
Where it is used
Used in roof weatherproofing assemblies.
Example sentence
Repair roof underlay tears before roofing continues.
Cladding termsWall underlay
Building wrap
Flexible wall underlay behind cladding.
Where it is used
Used before cavity battens and cladding.
Example sentence
Do not clad over torn building wrap.
Related trade
Builder / cladder
Cladding termsCladding
Cavity batten
Batten creating a drained cavity behind cladding.
Where it is used
Used behind many residential cladding systems.
Example sentence
Cavity battens must not block the drainage path.
Cladding termsCladding
Weatherboard
Overlapping cladding board used externally.
Where it is used
Used as wall cladding.
Example sentence
Check weatherboard end sealing and clearances.
Cladding termsCladding
Brick veneer
Outer brick cladding separated from framing by a cavity.
Where it is used
Used as an external wall cladding system.
Example sentence
Keep brick veneer cavity clean and weepholes open.
Cladding termsEnvelope
Flashing
Material/detail that directs water away from a junction.
Where it is used
Used at windows, roofs, cladding bases, corners, and penetrations.
Example sentence
The head flashing must be installed before cladding hides it.
Related trade
Roofer / cladder
Related compliance source
NZ Building Code E2 External moisture: Check E2/AS1, consented wall/roof details, cladding specifications, flashing details, and manufacturer installation requirements.
Cladding termsCladding
Scriber
Trim piece fitted beside weatherboards at joinery or corners.
Where it is used
Used with some weatherboard systems.
Example sentence
Paint or seal scriber cut ends as specified.
Roofing termsExterior
Soffit
Lining under roof eaves.
Where it is used
Used at eaves and roof overhangs.
Example sentence
Check soffit ventilation if specified.
Related trade
Builder / cladder
Roofing termsRoofing
Fascia
Board or metal edge member at roof eaves supporting gutters.
Where it is used
Used at roof perimeter.
Example sentence
Gutter brackets fix to the fascia.
Related trade
Roofer / builder
Drainage termsRoof drainage
Gutter
Channel collecting rainwater from the roof.
Where it is used
Used at roof edges.
Example sentence
Check gutter fall and outlet positions.
Related trade
Roofer / plumber
Related compliance source
NZ Building Code E1 Surface water: Check stormwater, surface water, drainage paths, and council/engineer stormwater design.
Drainage termsDrainage
Downpipe
Vertical pipe moving water from gutter to stormwater system.
Where it is used
Used on exterior walls.
Example sentence
Downpipes must connect to the stormwater system as designed.
Related trade
Roofer / drainlayer
Drainage termsDrainage
Inspection opening
Accessible point for drainage inspection and cleaning.
Where it is used
Used in drainage systems.
Example sentence
Do not bury an inspection opening under landscaping.
Drainage termsDrainage
Manhole
Access chamber for drainage or services.
Where it is used
Used in underground drainage/service networks.
Example sentence
Record manhole location and finished lid level.
Services termsServices
Rough-in
First installation of services before linings or finishes.
Where it is used
Used for plumbing, electrical, HVAC, data, and gas.
Example sentence
Photograph rough-ins before pre-line inspection.
Related trade
Services trades
Services termsFinishes
Fit-off
Final installation of fixtures, fittings, outlets, switches, appliances, and trims.
Where it is used
Used after linings/finishes are ready.
Example sentence
Electrical fit-off starts after painting is sufficiently complete.
Related trade
Services trades
Services termsPlumbing
Pressure test
Test to check pipework holds pressure and does not leak.
Where it is used
Used before cover-up and commissioning.
Example sentence
Record the plumbing pressure test in the daily report.
Quality termsAll stages
As-built
Record showing what was actually built or installed.
Where it is used
Used for services, drainage, structure, and handover.
Example sentence
Mark the as-built drainage route before backfill.
Related trade
Construction manager
Quality termsCloseout
Defect
Incomplete, damaged, incorrect, or poor-quality work that needs correction.
Where it is used
Used during QA, handover, and DLP.
Example sentence
The scratched door leaf is a handover defect.
Quality termsAll stages
Hold point
A point where work must stop until inspection, approval, or evidence is complete.
Where it is used
Used before pouring, backfilling, lining, cladding, tiling, or covering work.
Example sentence
Pre-pour inspection is a hold point.
Related trade
Construction manager
Handover termsHandover
Handover pack
Collected manuals, warranties, as-builts, certificates, keys, and maintenance information for the client.
Where it is used
Used at client handover.
Example sentence
The handover pack includes paint colours and appliance manuals.
Related trade
Construction manager