Desktop feasibility checklist

Use the Desktop feasibility checklist to turn property, title, planning, market, finance and site evidence into an explicit acquisition decision. It is a control aid, not a substitute for the current official, contractual or professionally prepared document where one governs.

Who initiates it

Client/developer or acquisition lead

Who fills it out

Client/developer, project manager or delegated document owner

Who reviews it

The project manager and the person with technical, contractual or commercial authority for the subject

Who approves it

Client/developer after lawyer, planner, finance and relevant technical advice

Applicability

Use before an offer where possible and complete every triggered investigation before the relevant SPA condition expires.

Who needs it

The project owner and the person controlling acquisition and due diligence, including each reviewer, approver or recipient named by the live project process.

Who signs it

Only the person with the authority or professional competence required by the source document, contract, insurer, lender or authority process.

When it is needed

Prepare before the related acquisition and due diligence decision or activity. Update it when scope, revision, cost, programme, responsibility, evidence or approval status changes.

Information needed

  • Property/title and SPA identifiers
  • Planning, hazard, services, access and physical constraints
  • Feasibility, market, finance and unresolved-condition status

Where to find the information

  • Current Record of Title, instruments, LIM and council property file
  • GeoMaps/Unitary Plan, survey and consultant reports
  • SPA, lender/valuer/market evidence and versioned feasibility

Step-by-step

How to prepare, review and file it

  1. 01Confirm whether this record applies to the project and who has authority to prepare, review, sign, submit and approve it.
  2. 02Download or open the current official form or source requirements when an authority, insurer, lender or contract controls the format.
  3. 03Gather the latest controlled source documents and confirm their revisions before entering information.
  4. 04Complete every field using project-specific facts; mark not applicable with a reason and clearly label unverified assumptions.
  5. 05Cross-check names, addresses, legal description, consent numbers, dates, values, drawing references, policy details and attachments.
  6. 06Have the appropriate project owner and qualified adviser review technical, legal, financial, insurance, safety and compliance content.
  7. 07Submit or issue it through the required channel, save proof of issue and record any response or RFI.
  8. 08Track actions to close-out, then save the final signed/accepted record and attachments in the controlled project file.

Where to submit or store it

Keep as a controlled internal project record and issue by the contract or project communication method when another party must review, approve or act on it.

Submission channels

  • Controlled project document system
  • Contract communication or document transmittal
  • Email only where the project communication plan permits it

Documents to attach

  • Current drawings, specifications, reports or approval documents referenced in the record
  • Marked-up plans, photographs, quotes, correspondence, inspection results or certificates that support the entries
  • Required signatures, declarations, schedules, evidence or authority-generated receipt/acknowledgement

What happens after issue or submission

Close or waive conditions only through the lawyer/authorised process, preserve source evidence and update feasibility and risk registers.

Controlled storage

Save the final record and supporting evidence in the controlled project document system, with the revision, issue status and related workspace record.

Source applicability

Confirm the project stage, contract, consent, consultant scope and actual site circumstances before use.

Common mistakes
  • Using an old template, superseded drawing, expired certificate or outdated authority process.
  • Copying generic wording without checking the specific property, consent, contract, policy or work package.
  • Leaving ownership, dates, revision, status, attachments or close-out evidence unclear.
  • Treating an internal checklist as an official authority, insurance, lender, legal or professional form.
Red flags and stop points
  • Required information conflicts between title, consented plans, consultant reports, contracts or site conditions.
  • A person is being asked to sign, certify or approve outside their authority or competence.
  • Work, purchase, payment, submission or occupation is proposed before a required approval or insurance confirmation is recorded.
  • Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.

Connected project controls

Related quote package
Due diligence and professional advice
Related checklist items
Acquisition and due diligence; Prepare and review Desktop feasibility checklist; File evidence and close outstanding actions
Related software tool
Document Management Register
Example completed version
Example: Desktop feasibility checklist for 12 Example Road, Auckland; prepared by the named project owner; current source documents listed by number and revision; assumptions marked; two actions assigned with dates; reviewed by the appropriate adviser; final version and evidence filed in the controlled project record.

Related problems

  • Title issue
  • Planning constraint missed
  • Feasibility no longer works
  • Service capacity unknown

Verification

Source / where to check

Use current official information and the controlled documents for the actual project.

Use Auckland Council property report pages to order or understand LIM reports, property files, custom resource consent reports, and related property information.

Use LINZ, a lawyer, and a licensed cadastral surveyor to verify Record of Title, legal description, interests, easements, covenants, consent notices, survey plans, and boundary/title matters.

Use GeoMaps as an early desktop check for property layers, contours, flooding/overland flow information, services context, and council spatial information. Confirm critical matters with professionals and council.

Relevant professional advice

Planner, surveyor, architect, engineer, quantity surveyor, lawyer, accountant, lender, valuer, real estate agent, and other project specialists must confirm site-specific decisions.

Project-specific consented documents and professional advice override generic guidance.

Educational resource and verification warning

BuildPath NZ is an educational guide and project-management resource only. It does not replace advice from Auckland Council, a planner, architect, engineer, surveyor, quantity surveyor, lawyer, accountant, lender, insurer, insurance broker, WorkSafe, Watercare, utility provider, building consent authority or other qualified professional.

Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.