Close-out, handover, defects and warrantiesBuildPath management templateUsually requiredHandover and close-outProject-controlledReviewed 11 August 2026
Defects period tracker
Use the Defects period tracker to prove that completion, authority, defect, as-built, warranty, operation and archive obligations are closed before handover or settlement. It is a control aid, not a substitute for the current official, contractual or professionally prepared document where one governs.
Who initiates it
Project manager, contract administrator or handover lead
Who fills it out
Client/developer, project manager or delegated document owner
Who reviews it
The project manager and the person with technical, contractual or commercial authority for the subject
Who approves it
Client/developer and the person authorised for the relevant completion/consent/contract decision
Applicability
Use from pre-practical-completion through the defects/warranty period and tailor it to the signed contract, consent and client/buyer requirements.
Who needs it
The project owner and the person controlling handover and close-out, including each reviewer, approver or recipient named by the live project process.
Who signs it
Only the person with the authority or professional competence required by the source document, contract, insurer, lender or authority process.
When it is needed
Prepare before the related handover and close-out decision or activity. Update it when scope, revision, cost, programme, responsibility, evidence or approval status changes.
Information needed
Completion/defect status and objective acceptance evidence
CCC, producer/trade certificates and as-builts
Warranties, manuals, keys, training, final account and archive
Where to find the information
Contract completion requirements and inspection records
Council/consultant/trade close-out records
Supplier warranties, manuals, as-builts and client acceptance
Step-by-step
How to prepare, review and file it
01Confirm whether this record applies to the project and who has authority to prepare, review, sign, submit and approve it.
02Download or open the current official form or source requirements when an authority, insurer, lender or contract controls the format.
03Gather the latest controlled source documents and confirm their revisions before entering information.
04Complete every field using project-specific facts; mark not applicable with a reason and clearly label unverified assumptions.
06Have the appropriate project owner and qualified adviser review technical, legal, financial, insurance, safety and compliance content.
07Submit or issue it through the required channel, save proof of issue and record any response or RFI.
08Track actions to close-out, then save the final signed/accepted record and attachments in the controlled project file.
Where to submit or store it
Keep as a controlled internal project record and issue by the contract or project communication method when another party must review, approve or act on it.
Submission channels
Controlled project document system
Contract communication or document transmittal
Email only where the project communication plan permits it
Documents to attach
Current drawings, specifications, reports or approval documents referenced in the record
Marked-up plans, photographs, quotes, correspondence, inspection results or certificates that support the entries
Required signatures, declarations, schedules, evidence or authority-generated receipt/acknowledgement
What happens after issue or submission
Verify completeness rather than file presence alone, issue the indexed pack, obtain acknowledgement and retain an immutable project archive plus residual-action tracker.
Controlled storage
Save the final record and supporting evidence in the controlled project document system, with the revision, issue status and related workspace record.
Source applicability
Confirm the project stage, contract, consent, consultant scope and actual site circumstances before use.
Common mistakes
Using an old template, superseded drawing, expired certificate or outdated authority process.
Copying generic wording without checking the specific property, consent, contract, policy or work package.
Leaving ownership, dates, revision, status, attachments or close-out evidence unclear.
Treating an internal checklist as an official authority, insurance, lender, legal or professional form.
Red flags and stop points
Required information conflicts between title, consented plans, consultant reports, contracts or site conditions.
A person is being asked to sign, certify or approve outside their authority or competence.
Work, purchase, payment, submission or occupation is proposed before a required approval or insurance confirmation is recorded.
Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.
Connected project controls
Related quote package
Relevant consultant, authority, supplier or trade package
Related checklist items
Handover and close-out; Prepare and review Defects period tracker; File evidence and close outstanding actions
Related software tool
Handover Pack Builder / Defects Tracker
Example completed version
Example: Defects period tracker for 12 Example Road, Auckland; prepared by the named project owner; current source documents listed by number and revision; assumptions marked; two actions assigned with dates; reviewed by the appropriate adviser; final version and evidence filed in the controlled project record.
BuildPath NZ is an educational guide and project-management resource only. It does not replace advice from Auckland Council, a planner, architect, engineer, surveyor, quantity surveyor, lawyer, accountant, lender, insurer, insurance broker, WorkSafe, Watercare, utility provider, building consent authority or other qualified professional.
Use current official information and the controlled documents for the actual project.
Project-controlled documents
Use the current project brief, approval authorities, issued drawings, specifications, contracts, consultant reports, programme, correspondence and controlled registers.
Relevant professional advice
Planner, surveyor, architect, engineer, quantity surveyor, lawyer, accountant, lender, valuer, real estate agent, and other project specialists must confirm site-specific decisions.
Project-specific consented documents and professional advice override generic guidance.
Educational resource and verification warning
BuildPath NZ is an educational guide and project-management resource only. It does not replace advice from Auckland Council, a planner, architect, engineer, surveyor, quantity surveyor, lawyer, accountant, lender, insurer, insurance broker, WorkSafe, Watercare, utility provider, building consent authority or other qualified professional.
Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.