BuildPath NZ logo

Finance

Bank will not fund the project

This can change development yield, consent pathway, purchase price, funding, construction cost, settlement timing, or legal risk. Treat it as a decision point, not background noise.

Finance and fundingCriticalbanklenderfinancefundingLast reviewed 11 August 2026

What it looks like

  • Lender declines, reduces loan amount, requires more equity, demands presales, or does not accept valuation/cost evidence.

Likely causes

  • Insufficient equity
  • valuation too low
  • developer experience
  • presale risk
  • cost risk
  • market conditions

Immediate action

  1. 1Pause the affected decision or commitment until the issue is understood.
  2. 2Record the issue in the risk register with date, source, owner, and next action.
  3. 3Send the relevant documents to Lender, Mortgage broker, Valuer and ask for written advice.
  4. 4Update feasibility, programme, budget, and decision register if cost, time, yield, consent, title, finance, or sales assumptions may change.

Step-by-step solution

  1. 1Define the problem in one sentence and identify which project decision it affects.
  2. 2Check the controlling documents: Loan application, Term sheet, Valuation, QS report, and related project records.
  3. 3Ask the responsible professional to confirm whether the issue is real, minor, manageable, or project-changing.
  4. 4List the available options: redesign, renegotiate, seek consent, add cost allowance, change programme, change sales strategy, or abandon.
  5. 5Price and programme each option using the current feasibility model.
  6. 6Make a written decision with source references and approval from the developer or project owner.
  7. 7Notify affected parties such as lender, lawyer, consultants, builder, agent, buyer, or council when required.

What not to do

  • Do not rely on a seller, agent, or builder comment when a planner, lawyer, accountant, engineer, surveyor, valuer, lender, or council needs to confirm it.
  • Do not hide the issue from the feasibility just because the project looked profitable yesterday.
  • Do not waive due diligence, lodge consent, sign a contract, approve a variation, or promise settlement while the issue is unresolved.
  • Do not give legal, tax, finance, planning, engineering, or council advice to others unless a qualified professional has confirmed it.

Verification

Source / where to check

Use current official information and the controlled documents for the actual project.

Relevant professional advice

Planner, surveyor, architect, engineer, quantity surveyor, lawyer, accountant, lender, valuer, real estate agent, and other project specialists must confirm site-specific decisions.

Project-specific consented documents and professional advice override generic guidance.

Cost impact

Critical if the developer cannot settle, build, or draw down funds.

Programme impact

High because purchase, construction, and settlement dates may be affected.

Risk level

Critical

Compliance and contract impact

Check whether the issue changes the resource consent pathway or conditions, building consent documents, consultant scope, sale and purchase conditions, finance terms, construction contract scope, notice requirements, variation process, or settlement obligations.

Example email / decision wording

Subject: Bank will not fund the project — advice and decision required. We identified this issue during finance and funding. The current evidence is listed in the attached record. Please confirm the controlling requirement, available options, cost/programme implications, further information needed, and whether any consent, contract, funding, or settlement action must pause. No assumption has been approved pending written advice.

Back to development problem solver