Closeout

Code Compliance Certificate

Compile and lodge the evidence council needs to decide whether completed work complies with the issued building consent.

ccccouncilrecordsproducer statements7 common tradesLast reviewed 11 August 2026

How to execute this stage

Micro-stage control plan

Work through each applicable step in order. A hold point means pause the dependent decision or work until the stated evidence and authorised review are complete.

3 structured steps
  1. 01Track every inspection, certificate, producer statement, LBP Record of Work, test result, and consent condition from the start of the projectLevel 2 · Closeout
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Track every inspection, certificate, producer statement, LBP Record of Work, test result, and consent condition from the start of the project.

    Technical context

    Coordinate this work against Consented drawings, Consent conditions, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: CCC delayed/refused. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Consented drawings is current, approved for the intended use, and available to the people doing the work.
    • Consent conditions and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the final council inspection sequence are confirmed.

    Checks

    • Check the completed work against Consented drawings and Consent conditions.
    • Check specifically for: CCC delayed/refused.
    • Avoid this known mistake: Waiting until the end to ask for certificates.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed code compliance certificate work before it is concealed.
    • Marked-up Consented drawings or a precise drawing/detail reference.
    • Final council inspection result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Final council inspection and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • CCC delayed/refused
    • Waiting until the end to ask for certificates
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Consented drawings
    • Consent conditions
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of code compliance certificate. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Resolve failed inspections, amendments, minor variations, and outstanding council requests before applying for CCC.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

  2. 02Resolve failed inspections, amendments, minor variations, and outstanding council requests before applying for CCCLevel 2 · Closeout
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Resolve failed inspections, amendments, minor variations, and outstanding council requests before applying for CCC.

    Technical context

    Coordinate this work against Approved amendments, Council CCC requirements, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Missing Record of Work. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Approved amendments is current, approved for the intended use, and available to the people doing the work.
    • Council CCC requirements and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the document review sequence are confirmed.

    Checks

    • Check the completed work against Approved amendments and Council CCC requirements.
    • Check specifically for: Missing Record of Work.
    • Avoid this known mistake: Not tracking failed inspections.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed code compliance certificate work before it is concealed.
    • Marked-up Approved amendments or a precise drawing/detail reference.
    • Document review result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Document review and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Missing Record of Work
    • Not tracking failed inspections
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Approved amendments
    • Council CCC requirements
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of code compliance certificate. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Submit a complete CCC pack and respond quickly to council requests.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

  3. 03Submit a complete CCC pack and respond quickly to council requestsLevel 2 · Closeout
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Submit a complete CCC pack and respond quickly to council requests.

    Technical context

    Coordinate this work against Minor variation records, Producer statement requirements, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Unapproved change. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Minor variation records is current, approved for the intended use, and available to the people doing the work.
    • Producer statement requirements and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the ccc application review sequence are confirmed.

    Checks

    • Check the completed work against Minor variation records and Producer statement requirements.
    • Check specifically for: Unapproved change.
    • Avoid this known mistake: Submitting incomplete CCC pack.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed code compliance certificate work before it is concealed.
    • Marked-up Minor variation records or a precise drawing/detail reference.
    • CCC application review result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until CCC application review and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Unapproved change
    • Submitting incomplete CCC pack
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Minor variation records
    • Producer statement requirements
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of code compliance certificate. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Close the code compliance certificate stage, link its evidence, resolve outstanding defects and release only the next applicable stage.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

Trade-to-trade control

Interfaces and release gates

Use the actual consented design, specification and authorised reviewers. These controls help expose gaps; they do not approve work.

Civil drainage, building services and final ground levels

Prerequisites

  • Civil, drainage, architectural and landscape drawings use coordinated levels
  • Connection approvals, easements and authority requirements are known
  • Service crossings, retaining, access and future maintenance zones are resolved

Interface checks

  • Pipe grades, cover, bedding, separation and test points meet the approved design
  • Finished ground/paving falls do not compromise cladding, thresholds or overland flow
  • As-built survey can identify every buried service and connection
Hold point: Do not backfill or complete hard landscaping until underground work is inspected/tested, located and recorded for the as-built file.

Evidence before release

  • Open-trench photographs and test results
  • Survey/as-built information
  • Authority/council/engineer acceptance required for the actual project

Next team: External works, landscaping and close-out teams

Open the related Workspace control →

Trade completion, inspection and handover evidence

Prerequisites

  • Trade defects and outstanding tests are visible in the registers
  • Consent/contract/authority deliverables have named owners
  • The current drawing, variation and product records are reconciled

Interface checks

  • A reported completion is not treated as verified without evidence
  • Failed inspections and defects link to corrective work and re-check
  • Handover/CCC files identify missing, submitted, accepted and not-applicable items separately
Hold point: Do not represent the project, a trade package, CCC file or handover pack as complete while required evidence, acceptance or unresolved source conflicts remain.

Evidence before release

  • Closed inspection and defect records
  • As-builts, certificates, warranties and Records of Work
  • Dated handover/CCC index with source and review status

Next team: Owner, facilities/maintenance contact or defects team

Open the related Workspace control →

What happens in this stage

  • Track every inspection, certificate, producer statement, LBP Record of Work, test result, and consent condition from the start of the project.
  • Resolve failed inspections, amendments, minor variations, and outstanding council requests before applying for CCC.
  • Submit a complete CCC pack and respond quickly to council requests.

Before work starts

  • Confirm the latest issued-for-construction and consented documents for code compliance certificate are on site, including Consented drawings.
  • Check Consent conditions, approved product data, RFIs, minor variations, and amendment status before work starts.
  • Confirm the subcontractor understands the scope, hold points, access, protection requirements, H&S controls, and quality evidence required.
  • Check the programme sequence so this stage does not start before earlier work, inspections, testing, or concealed-work photos are complete.
  • Confirm materials delivered to site match the specification, are dry/undamaged, and are stored according to manufacturer instructions.

During the work

  • Walk the work face early, mid-shift, and before close-up. Compare actual work with the consented drawings, specification, and manufacturer details.
  • Check set-out, levels, falls, clearances, penetrations, fixings, bracing, waterproofing, or protection points that will be difficult to see later.
  • Ask trades to show their own quality checks rather than only saying the work is complete.
  • Keep weather, site condition, delivery, delay, inspection, RFI, variation, and safety notes in the daily report.
  • Photograph any work before it is covered, backfilled, lined, clad, tiled, painted, or otherwise hidden.

After the work

  • Complete a close-out walk with the subcontractor and mark defects immediately while access is still available.
  • Confirm required inspection bookings, council results, producer statements, LBP Records of Work, warranties, test certificates, or installer declarations are obtained.
  • Update as-built notes where service routes, drainage, fixings, penetrations, or dimensions differ from the design.
  • Confirm the area is protected from weather, other trades, impact damage, contamination, or premature loading.
  • Update the lookahead programme and tell affected trades what is ready, what is blocked, and what must not be covered.

Common problems and step-by-step solutions

Missing producer statement
  1. 1Stop the affected code compliance certificate activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
CCC request for more information
  1. 1Stop the affected code compliance certificate activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Unapproved site change
  1. 1Stop the affected code compliance certificate activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.

Verification

Source / where to check

Use current official information and the controlled documents for the actual project.

Auckland Council explains local building consent processes, CCC, related certificates, producer statements, LBP notification, and whether resource consent may also be needed.

MBIE guidance explains that work should be built to the issued building consent, inspections must be managed, and records/certificates should be kept for CCC.

Use when a site change may require a minor variation or amendment before work continues.

Consented drawings and specifications

The issued consent drawings, stamped specifications, engineering drawings, RFIs, minor variations, and amendments control the specific project.

Manufacturer specification

Use the exact current installation manual, warranty requirements, BRANZ/Appraisal information where applicable, and product data sheet for the product on site.

Insufficient data to verify

Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.

Project-specific consented documents and professional advice override generic guidance.

Common inspections required

  • Final council inspection
  • Document review
  • CCC application review

Common risks

  • CCC delayed/refused
  • Missing Record of Work
  • Unapproved change
  • Producer statement not accepted

Common mistakes

  • Waiting until the end to ask for certificates
  • Not tracking failed inspections
  • Submitting incomplete CCC pack

Required documentation

  • Latest consented drawings and specifications
  • Relevant RFIs, site instructions, amendments, minor variations, and variation approvals
  • Subcontractor scope, QA checklist, delivery dockets, product data, and installation records
  • Inspection booking/result records and photos before cover-up
  • Daily site report notes covering labour, weather, progress, delays, risks, and decisions

Photos or diagrams needed

  • Wide photo showing where code compliance certificate is happening on the site
  • Close-up photos of critical details, fixings, laps, seals, penetrations, clearances, levels, or falls
  • Photo of product labels, batch numbers, delivery dockets, and installer marks where relevant
  • Marked-up drawing or simple diagram showing any changed location, clash, defect, or agreed remedial detail

Construction manager checklist

  1. 1Scope, drawings, specification, product data, and latest revision confirmed
  2. 2Trade briefed on hold points, tolerances to verify, evidence required, and inspection sequence
  3. 3Access, storage, protection, temporary works, and safety controls in place
  4. 4Work checked against drawings during installation, not only at completion
  5. 5Photos and records captured before work is concealed
  6. 6Defects, RFIs, delays, and variations recorded with owner and due date
  7. 7Inspection/producer statement/warranty/Record of Work requirements tracked for CCC

Questions to ask the subcontractor

  • Which drawing, detail, or manufacturer instruction are you working from?
  • What needs to be checked before this is covered or handed to the next trade?
  • What could stop you today: weather, access, materials, information, inspections, or other trades?
  • Does anything on site differ from the drawings or specification?
  • What evidence will you provide for the quality file and CCC file?

Red flags to stop work

  • Work differs from consented drawings or specification and no approved variation/RFI exists
  • A structural, weathertightness, waterproofing, drainage, fire/safety, or H1 detail is unclear
  • The trade wants to cover work before inspection, testing, or photos are complete
  • Specified materials are missing, substituted, damaged, wet, expired, or installed outside manufacturer instructions
  • A safety control is missing for excavation, heights, plant movement, electrical work, asbestos, silica, or public protection

What to record in the daily report

  • Exact location and quantity of work completed
  • Trade headcount, company names, plant used, deliveries, and material batch/product details
  • Weather, site conditions, delays, instructions received, RFIs raised, and inspections booked/passed/failed
  • Photos taken before cover-up and any defects or non-conformances found
  • Next-day lookahead, blockers, and who is responsible for each action