Maintenance period / defects liability period

Track, triage, assign, fix, and close defects or warranty items reported after handover, while protecting records and client relationship.

dlpmaintenancedefectspost-handover5 common tradesLast reviewed 11 August 2026

How to execute this stage

Micro-stage control plan

Work through each applicable step in order. A hold point means pause the dependent decision or work until the stated evidence and authorised review are complete.

3 structured steps
  1. 01Maintain a DLP/maintenance defect log with date, location, photo, category, responsible trade, action, appointment, and close-out evidenceLevel 2 · Post-construction
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Maintain a DLP/maintenance defect log with date, location, photo, category, responsible trade, action, appointment, and close-out evidence.

    Technical context

    Coordinate this work against As-built drawings, Contract DLP/maintenance requirements, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Urgent defect not actioned. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • As-built drawings is current, approved for the intended use, and available to the people doing the work.
    • Contract DLP/maintenance requirements and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the dlp inspection sequence are confirmed.

    Checks

    • Check the completed work against As-built drawings and Contract DLP/maintenance requirements.
    • Check specifically for: Urgent defect not actioned.
    • Avoid this known mistake: No single defect log.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed maintenance period / defects liability period work before it is concealed.
    • Marked-up As-built drawings or a precise drawing/detail reference.
    • DLP inspection result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until DLP inspection and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Urgent defect not actioned
    • No single defect log
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • As-built drawings
    • Contract DLP/maintenance requirements
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of maintenance period / defects liability period. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Separate urgent safety/water/electrical issues from cosmetic settlement or normal maintenance.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

  2. 02Separate urgent safety/water/electrical issues from cosmetic settlement or normal maintenanceLevel 2 · Post-construction
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Separate urgent safety/water/electrical issues from cosmetic settlement or normal maintenance.

    Technical context

    Coordinate this work against Product manuals, Warranty terms, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Warranty voided by poor maintenance. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Product manuals is current, approved for the intended use, and available to the people doing the work.
    • Warranty terms and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the warranty inspection sequence are confirmed.

    Checks

    • Check the completed work against Product manuals and Warranty terms.
    • Check specifically for: Warranty voided by poor maintenance.
    • Avoid this known mistake: Arguing before inspecting.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed maintenance period / defects liability period work before it is concealed.
    • Marked-up Product manuals or a precise drawing/detail reference.
    • Warranty inspection result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Warranty inspection and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Warranty voided by poor maintenance
    • Arguing before inspecting
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Product manuals
    • Warranty terms
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of maintenance period / defects liability period. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Complete planned DLP inspection and process final retentions/release obligations according to contract.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

  3. 03Complete planned DLP inspection and process final retentions/release obligations according to contractLevel 2 · Post-construction
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Complete planned DLP inspection and process final retentions/release obligations according to contract.

    Technical context

    Coordinate this work against Warranty documents, Manufacturer maintenance instructions, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Poor record trail. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Warranty documents is current, approved for the intended use, and available to the people doing the work.
    • Manufacturer maintenance instructions and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the close-out reinspection sequence are confirmed.

    Checks

    • Check the completed work against Warranty documents and Manufacturer maintenance instructions.
    • Check specifically for: Poor record trail.
    • Avoid this known mistake: Closing item without photo/sign-off.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed maintenance period / defects liability period work before it is concealed.
    • Marked-up Warranty documents or a precise drawing/detail reference.
    • Close-out reinspection result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Close-out reinspection and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Poor record trail
    • Closing item without photo/sign-off
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Warranty documents
    • Manufacturer maintenance instructions
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of maintenance period / defects liability period. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Close the maintenance period / defects liability period stage, link its evidence, resolve outstanding defects and release only the next applicable stage.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

Trade-to-trade control

Interfaces and release gates

Use the actual consented design, specification and authorised reviewers. These controls help expose gaps; they do not approve work.

Trade completion, inspection and handover evidence

Prerequisites

  • Trade defects and outstanding tests are visible in the registers
  • Consent/contract/authority deliverables have named owners
  • The current drawing, variation and product records are reconciled

Interface checks

  • A reported completion is not treated as verified without evidence
  • Failed inspections and defects link to corrective work and re-check
  • Handover/CCC files identify missing, submitted, accepted and not-applicable items separately
Hold point: Do not represent the project, a trade package, CCC file or handover pack as complete while required evidence, acceptance or unresolved source conflicts remain.

Evidence before release

  • Closed inspection and defect records
  • As-builts, certificates, warranties and Records of Work
  • Dated handover/CCC index with source and review status

Next team: Owner, facilities/maintenance contact or defects team

Open the related Workspace control →

What happens in this stage

  • Maintain a DLP/maintenance defect log with date, location, photo, category, responsible trade, action, appointment, and close-out evidence.
  • Separate urgent safety/water/electrical issues from cosmetic settlement or normal maintenance.
  • Complete planned DLP inspection and process final retentions/release obligations according to contract.

Before work starts

  • Confirm the latest issued-for-construction and consented documents for maintenance period / defects liability period are on site, including As-built drawings.
  • Check Contract DLP/maintenance requirements, approved product data, RFIs, minor variations, and amendment status before work starts.
  • Confirm the subcontractor understands the scope, hold points, access, protection requirements, H&S controls, and quality evidence required.
  • Check the programme sequence so this stage does not start before earlier work, inspections, testing, or concealed-work photos are complete.
  • Confirm materials delivered to site match the specification, are dry/undamaged, and are stored according to manufacturer instructions.

During the work

  • Walk the work face early, mid-shift, and before close-up. Compare actual work with the consented drawings, specification, and manufacturer details.
  • Check set-out, levels, falls, clearances, penetrations, fixings, bracing, waterproofing, or protection points that will be difficult to see later.
  • Ask trades to show their own quality checks rather than only saying the work is complete.
  • Keep weather, site condition, delivery, delay, inspection, RFI, variation, and safety notes in the daily report.
  • Photograph any work before it is covered, backfilled, lined, clad, tiled, painted, or otherwise hidden.

After the work

  • Complete a close-out walk with the subcontractor and mark defects immediately while access is still available.
  • Confirm required inspection bookings, council results, producer statements, LBP Records of Work, warranties, test certificates, or installer declarations are obtained.
  • Update as-built notes where service routes, drainage, fixings, penetrations, or dimensions differ from the design.
  • Confirm the area is protected from weather, other trades, impact damage, contamination, or premature loading.
  • Update the lookahead programme and tell affected trades what is ready, what is blocked, and what must not be covered.

Common problems and step-by-step solutions

Door sticking after handover
  1. 1Stop the affected maintenance period / defects liability period activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Minor plumbing leak
  1. 1Stop the affected maintenance period / defects liability period activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Trade recall delay
  1. 1Stop the affected maintenance period / defects liability period activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.

Verification

Source / where to check

Use current official information and the controlled documents for the actual project.

Consented drawings and specifications

The issued consent drawings, stamped specifications, engineering drawings, RFIs, minor variations, and amendments control the specific project.

Manufacturer specification

Use the exact current installation manual, warranty requirements, BRANZ/Appraisal information where applicable, and product data sheet for the product on site.

Insufficient data to verify

Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.

Consented drawings and specifications

The issued consent drawings, stamped specifications, engineering drawings, RFIs, minor variations, and amendments control the specific project.

Manufacturer specification

Use the exact current installation manual, warranty requirements, BRANZ/Appraisal information where applicable, and product data sheet for the product on site.

Insufficient data to verify

Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.

Project-specific consented documents and professional advice override generic guidance.

Common inspections required

  • DLP inspection
  • Warranty inspection
  • Close-out reinspection

Common risks

  • Urgent defect not actioned
  • Warranty voided by poor maintenance
  • Poor record trail
  • Trade recall delays

Common mistakes

  • No single defect log
  • Arguing before inspecting
  • Closing item without photo/sign-off

Required documentation

  • Latest consented drawings and specifications
  • Relevant RFIs, site instructions, amendments, minor variations, and variation approvals
  • Subcontractor scope, QA checklist, delivery dockets, product data, and installation records
  • Inspection booking/result records and photos before cover-up
  • Daily site report notes covering labour, weather, progress, delays, risks, and decisions

Photos or diagrams needed

  • Wide photo showing where maintenance period / defects liability period is happening on the site
  • Close-up photos of critical details, fixings, laps, seals, penetrations, clearances, levels, or falls
  • Photo of product labels, batch numbers, delivery dockets, and installer marks where relevant
  • Marked-up drawing or simple diagram showing any changed location, clash, defect, or agreed remedial detail

Construction manager checklist

  1. 1Scope, drawings, specification, product data, and latest revision confirmed
  2. 2Trade briefed on hold points, tolerances to verify, evidence required, and inspection sequence
  3. 3Access, storage, protection, temporary works, and safety controls in place
  4. 4Work checked against drawings during installation, not only at completion
  5. 5Photos and records captured before work is concealed
  6. 6Defects, RFIs, delays, and variations recorded with owner and due date
  7. 7Inspection/producer statement/warranty/Record of Work requirements tracked for CCC

Questions to ask the subcontractor

  • Which drawing, detail, or manufacturer instruction are you working from?
  • What needs to be checked before this is covered or handed to the next trade?
  • What could stop you today: weather, access, materials, information, inspections, or other trades?
  • Does anything on site differ from the drawings or specification?
  • What evidence will you provide for the quality file and CCC file?

Red flags to stop work

  • Work differs from consented drawings or specification and no approved variation/RFI exists
  • A structural, weathertightness, waterproofing, drainage, fire/safety, or H1 detail is unclear
  • The trade wants to cover work before inspection, testing, or photos are complete
  • Specified materials are missing, substituted, damaged, wet, expired, or installed outside manufacturer instructions
  • A safety control is missing for excavation, heights, plant movement, electrical work, asbestos, silica, or public protection

What to record in the daily report

  • Exact location and quantity of work completed
  • Trade headcount, company names, plant used, deliveries, and material batch/product details
  • Weather, site conditions, delays, instructions received, RFIs raised, and inspections booked/passed/failed
  • Photos taken before cover-up and any defects or non-conformances found
  • Next-day lookahead, blockers, and who is responsible for each action