Site start
Site establishment
Convert the residential property into a controlled site with safe access, welfare, storage, temporary services, protection, and emergency arrangements.
How to execute this stage
Micro-stage control plan
Work through each applicable step in order. A hold point means pause the dependent decision or work until the stated evidence and authorised review are complete.
01Set site boundaries, access routes, delivery zones, waste areas, emergency assembly point, first aid, toilets, and material storageLevel 2 · Site start
TaskCheckHold pointEvidenceRecordNext actionSimple explanation
Set site boundaries, access routes, delivery zones, waste areas, emergency assembly point, first aid, toilets, and material storage.
Technical context
Coordinate this work against Site plan, H&S plan, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.
Why it matters: The main recorded risk is: Unauthorised access. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.
Prerequisites
- Site plan is current, approved for the intended use, and available to the people doing the work.
- H&S plan and relevant product information have been checked.
- Access, responsibility, safety controls, preceding work and the site establishment check sequence are confirmed.
Checks
- Check the completed work against Site plan and H&S plan.
- Check specifically for: Unauthorised access.
- Avoid this known mistake: No clear delivery route.
Evidence to save
- Wide, location-identifying and close-up photographs of the completed site establishment work before it is concealed.
- Marked-up Site plan or a precise drawing/detail reference.
- Site establishment check result, consultant record, trade QA record or written not-applicable reason.
Hold point
Do not cover, backfill, load, connect, certify or release the next activity until Site establishment check and the required project evidence are complete or the authorised reviewer confirms what may proceed.
Stop or escalate when
- Unauthorised access
- No clear delivery route
- The current drawing, approval, competent reviewer or required evidence cannot be confirmed.
Documents and records
- Site plan
- H&S plan
- Current RFI/site-instruction/change record
- Inspection and evidence register
- Cost effect
- Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of site establishment. Record the cause and obtain written pricing before approving a commercial change.
- Programme effect
- This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.
Next action
Brief neighbours where appropriate and protect public footpaths, driveways, existing structures, trees, and services.
Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.
Use the current consented/issued project documents and competent site review. BuildPath does not approve work.
02Brief neighbours where appropriate and protect public footpaths, driveways, existing structures, trees, and servicesLevel 2 · Site start
TaskCheckHold pointEvidenceRecordNext actionSimple explanation
Brief neighbours where appropriate and protect public footpaths, driveways, existing structures, trees, and services.
Technical context
Coordinate this work against Traffic/access plan, Environmental controls plan, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.
Why it matters: The main recorded risk is: Public injury. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.
Prerequisites
- Traffic/access plan is current, approved for the intended use, and available to the people doing the work.
- Environmental controls plan and relevant product information have been checked.
- Access, responsibility, safety controls, preceding work and the temporary electrical check sequence are confirmed.
Checks
- Check the completed work against Traffic/access plan and Environmental controls plan.
- Check specifically for: Public injury.
- Avoid this known mistake: No visitor sign-in.
Evidence to save
- Wide, location-identifying and close-up photographs of the completed site establishment work before it is concealed.
- Marked-up Traffic/access plan or a precise drawing/detail reference.
- Temporary electrical check result, consultant record, trade QA record or written not-applicable reason.
Hold point
Do not cover, backfill, load, connect, certify or release the next activity until Temporary electrical check and the required project evidence are complete or the authorised reviewer confirms what may proceed.
Stop or escalate when
- Public injury
- No visitor sign-in
- The current drawing, approval, competent reviewer or required evidence cannot be confirmed.
Documents and records
- Traffic/access plan
- Environmental controls plan
- Current RFI/site-instruction/change record
- Inspection and evidence register
- Cost effect
- Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of site establishment. Record the cause and obtain written pricing before approving a commercial change.
- Programme effect
- This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.
Next action
Start site induction, visitor control, daily reporting, hazard register, and emergency plan.
Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.
Use the current consented/issued project documents and competent site review. BuildPath does not approve work.
03Start site induction, visitor control, daily reporting, hazard register, and emergency planLevel 2 · Site start
TaskCheckHold pointEvidenceRecordNext actionSimple explanation
Start site induction, visitor control, daily reporting, hazard register, and emergency plan.
Technical context
Coordinate this work against Service location plan, Neighbour/property protection requirements, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.
Why it matters: The main recorded risk is: Poor site drainage. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.
Prerequisites
- Service location plan is current, approved for the intended use, and available to the people doing the work.
- Neighbour/property protection requirements and relevant product information have been checked.
- Access, responsibility, safety controls, preceding work and the public protection check sequence are confirmed.
Checks
- Check the completed work against Service location plan and Neighbour/property protection requirements.
- Check specifically for: Poor site drainage.
- Avoid this known mistake: Insufficient welfare.
Evidence to save
- Wide, location-identifying and close-up photographs of the completed site establishment work before it is concealed.
- Marked-up Service location plan or a precise drawing/detail reference.
- Public protection check result, consultant record, trade QA record or written not-applicable reason.
Hold point
Do not cover, backfill, load, connect, certify or release the next activity until Public protection check and the required project evidence are complete or the authorised reviewer confirms what may proceed.
Stop or escalate when
- Poor site drainage
- Insufficient welfare
- The current drawing, approval, competent reviewer or required evidence cannot be confirmed.
Documents and records
- Service location plan
- Neighbour/property protection requirements
- Current RFI/site-instruction/change record
- Inspection and evidence register
- Cost effect
- Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of site establishment. Record the cause and obtain written pricing before approving a commercial change.
- Programme effect
- This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.
Next action
Close the site establishment stage, link its evidence, resolve outstanding defects and release only the next applicable stage.
Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.
Use the current consented/issued project documents and competent site review. BuildPath does not approve work.
Trade-to-trade control
Interfaces and release gates
Use the actual consented design, specification and authorised reviewers. These controls help expose gaps; they do not approve work.
Release this stage to the next team
Prerequisites
- • Current consented/contract documents and scope are available
- • Preceding work, access, safety and materials are ready
- • Named people own open RFIs, defects, inspections and evidence
Interface checks
- • Work matches the current documents and actual site condition
- • Interfaces with the preceding and following trades have been walked
- • Cost, programme, change and evidence consequences are recorded
Evidence before release
- • Location and detail photographs
- • Dated checklist/inspection/RFI references
- • Daily report and linked action/defect records
Next team: The next applicable project team
Open the related Workspace control →What happens in this stage
- Set site boundaries, access routes, delivery zones, waste areas, emergency assembly point, first aid, toilets, and material storage.
- Brief neighbours where appropriate and protect public footpaths, driveways, existing structures, trees, and services.
- Start site induction, visitor control, daily reporting, hazard register, and emergency plan.
Before work starts
- Confirm the latest issued-for-construction and consented documents for site establishment are on site, including Site plan.
- Check H&S plan, approved product data, RFIs, minor variations, and amendment status before work starts.
- Confirm the subcontractor understands the scope, hold points, access, protection requirements, H&S controls, and quality evidence required.
- Check the programme sequence so this stage does not start before earlier work, inspections, testing, or concealed-work photos are complete.
- Confirm materials delivered to site match the specification, are dry/undamaged, and are stored according to manufacturer instructions.
During the work
- Walk the work face early, mid-shift, and before close-up. Compare actual work with the consented drawings, specification, and manufacturer details.
- Check set-out, levels, falls, clearances, penetrations, fixings, bracing, waterproofing, or protection points that will be difficult to see later.
- Ask trades to show their own quality checks rather than only saying the work is complete.
- Keep weather, site condition, delivery, delay, inspection, RFI, variation, and safety notes in the daily report.
- Photograph any work before it is covered, backfilled, lined, clad, tiled, painted, or otherwise hidden.
After the work
- Complete a close-out walk with the subcontractor and mark defects immediately while access is still available.
- Confirm required inspection bookings, council results, producer statements, LBP Records of Work, warranties, test certificates, or installer declarations are obtained.
- Update as-built notes where service routes, drainage, fixings, penetrations, or dimensions differ from the design.
- Confirm the area is protected from weather, other trades, impact damage, contamination, or premature loading.
- Update the lookahead programme and tell affected trades what is ready, what is blocked, and what must not be covered.
Common problems and step-by-step solutions
Site access too narrow
- 1Stop the affected site establishment activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
- 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
- 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
- 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
- 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
- 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Neighbour complains about damage/noise
- 1Stop the affected site establishment activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
- 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
- 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
- 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
- 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
- 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Temporary power or water not ready
- 1Stop the affected site establishment activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
- 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
- 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
- 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
- 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
- 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Verification
Source / where to check
Use current official information and the controlled documents for the actual project.
Use WorkSafe NZ for construction health and safety duties, risk management, and practical guidance for residential construction work.
Auckland Council explains local building consent processes, CCC, related certificates, producer statements, LBP notification, and whether resource consent may also be needed.
The issued consent drawings, stamped specifications, engineering drawings, RFIs, minor variations, and amendments control the specific project.
Use the exact current installation manual, warranty requirements, BRANZ/Appraisal information where applicable, and product data sheet for the product on site.
Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.
Project-specific consented documents and professional advice override generic guidance.
Common inspections required
- Site establishment check
- Temporary electrical check
- Public protection check
Common risks
- Unauthorised access
- Public injury
- Poor site drainage
- Materials blocking access
- Damage to neighbouring property
Common mistakes
- No clear delivery route
- No visitor sign-in
- Insufficient welfare
- Storage causing trip hazards or water damage
Required documentation
- Latest consented drawings and specifications
- Relevant RFIs, site instructions, amendments, minor variations, and variation approvals
- Subcontractor scope, QA checklist, delivery dockets, product data, and installation records
- Inspection booking/result records and photos before cover-up
- Daily site report notes covering labour, weather, progress, delays, risks, and decisions
Photos or diagrams needed
- Wide photo showing where site establishment is happening on the site
- Close-up photos of critical details, fixings, laps, seals, penetrations, clearances, levels, or falls
- Photo of product labels, batch numbers, delivery dockets, and installer marks where relevant
- Marked-up drawing or simple diagram showing any changed location, clash, defect, or agreed remedial detail
Construction manager checklist
- 1Scope, drawings, specification, product data, and latest revision confirmed
- 2Trade briefed on hold points, tolerances to verify, evidence required, and inspection sequence
- 3Access, storage, protection, temporary works, and safety controls in place
- 4Work checked against drawings during installation, not only at completion
- 5Photos and records captured before work is concealed
- 6Defects, RFIs, delays, and variations recorded with owner and due date
- 7Inspection/producer statement/warranty/Record of Work requirements tracked for CCC
Questions to ask the subcontractor
- Which drawing, detail, or manufacturer instruction are you working from?
- What needs to be checked before this is covered or handed to the next trade?
- What could stop you today: weather, access, materials, information, inspections, or other trades?
- Does anything on site differ from the drawings or specification?
- What evidence will you provide for the quality file and CCC file?
Red flags to stop work
- Work differs from consented drawings or specification and no approved variation/RFI exists
- A structural, weathertightness, waterproofing, drainage, fire/safety, or H1 detail is unclear
- The trade wants to cover work before inspection, testing, or photos are complete
- Specified materials are missing, substituted, damaged, wet, expired, or installed outside manufacturer instructions
- A safety control is missing for excavation, heights, plant movement, electrical work, asbestos, silica, or public protection
What to record in the daily report
- Exact location and quantity of work completed
- Trade headcount, company names, plant used, deliveries, and material batch/product details
- Weather, site conditions, delays, instructions received, RFIs raised, and inspections booked/passed/failed
- Photos taken before cover-up and any defects or non-conformances found
- Next-day lookahead, blockers, and who is responsible for each action