Internal linings

Fix plasterboard, bracing linings, wet-area linings, fire/acoustic linings where specified, and stopping systems only after pre-line checks are complete.

liningsplasterboardbracingpre-line6 common tradesLast reviewed 11 August 2026

How to execute this stage

Micro-stage control plan

Work through each applicable step in order. A hold point means pause the dependent decision or work until the stated evidence and authorised review are complete.

3 structured steps
  1. 01Confirm framing, services, insulation, bracing, moisture, and inspection status before lining startsLevel 2 · Interior
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Confirm framing, services, insulation, bracing, moisture, and inspection status before lining starts.

    Technical context

    Coordinate this work against Wall lining plan, Plasterboard manufacturer manual, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Bracing not fixed correctly. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Wall lining plan is current, approved for the intended use, and available to the people doing the work.
    • Plasterboard manufacturer manual and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the pre-line inspection sequence are confirmed.

    Checks

    • Check the completed work against Wall lining plan and Plasterboard manufacturer manual.
    • Check specifically for: Bracing not fixed correctly.
    • Avoid this known mistake: Lining before inspection passed.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed internal linings work before it is concealed.
    • Marked-up Wall lining plan or a precise drawing/detail reference.
    • Pre-line inspection result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Pre-line inspection and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Bracing not fixed correctly
    • Lining before inspection passed
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Wall lining plan
    • Plasterboard manufacturer manual
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of internal linings. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Check sheet type, thickness, bracing/fixing pattern, wet-area board locations, control joints, and penetrations.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

  2. 02Check sheet type, thickness, bracing/fixing pattern, wet-area board locations, control joints, and penetrationsLevel 2 · Interior
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Check sheet type, thickness, bracing/fixing pattern, wet-area board locations, control joints, and penetrations.

    Technical context

    Coordinate this work against Bracing plan, Bracing system specification, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Wet framing enclosed. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Bracing plan is current, approved for the intended use, and available to the people doing the work.
    • Bracing system specification and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the bracing lining check sequence are confirmed.

    Checks

    • Check the completed work against Bracing plan and Bracing system specification.
    • Check specifically for: Wet framing enclosed.
    • Avoid this known mistake: Wrong screw spacing for bracing.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed internal linings work before it is concealed.
    • Marked-up Bracing plan or a precise drawing/detail reference.
    • Bracing lining check result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Bracing lining check and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Wet framing enclosed
    • Wrong screw spacing for bracing
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Bracing plan
    • Bracing system specification
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of internal linings. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Record concealed evidence and protect finished surfaces.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

  3. 03Record concealed evidence and protect finished surfacesLevel 2 · Interior
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Record concealed evidence and protect finished surfaces.

    Technical context

    Coordinate this work against Interior elevations, Wet-area lining specification, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Wrong board in wet area. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Interior elevations is current, approved for the intended use, and available to the people doing the work.
    • Wet-area lining specification and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the internal qa before stopping sequence are confirmed.

    Checks

    • Check the completed work against Interior elevations and Wet-area lining specification.
    • Check specifically for: Wrong board in wet area.
    • Avoid this known mistake: No access panel where needed.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed internal linings work before it is concealed.
    • Marked-up Interior elevations or a precise drawing/detail reference.
    • Internal QA before stopping result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Internal QA before stopping and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Wrong board in wet area
    • No access panel where needed
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Interior elevations
    • Wet-area lining specification
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of internal linings. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Close the internal linings stage, link its evidence, resolve outstanding defects and release only the next applicable stage.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

Trade-to-trade control

Interfaces and release gates

Use the actual consented design, specification and authorised reviewers. These controls help expose gaps; they do not approve work.

Structure, penetrations and building services

Prerequisites

  • Coordinated services routes and fixture/equipment positions are issued
  • Restricted drilling/notching zones and fire/acoustic systems are identified
  • Required sleeves, supports and access panels are agreed

Interface checks

  • No member, brace, connection or fire/acoustic element is altered without authorised detail
  • Falls, ventilation paths, clearances and maintenance access can still be achieved
  • Penetration sealing system matches substrate, service and required rating
Hold point: Do not drill, notch, core, close walls/ceilings or commission a concealed route until clashes and penetrations are authorised and photographed.

Evidence before release

  • Coordinated services drawing or marked-up route
  • Pre-line photographs of every concealed service zone
  • Engineer/designer RFI response and penetration schedule where required

Next team: Insulation, lining and commissioning teams

Open the related Workspace control →

Wet-area structure, plumbing, waterproofing and finishes

Prerequisites

  • Substrate type, stiffness, falls and moisture condition are acceptable
  • Waste positions, flange details, taps and penetrations match the waterproofing design
  • Membrane, adhesive, sealant and finish systems are compatible

Interface checks

  • Falls run to wastes without ponding and door/transition levels work
  • Junctions, movement joints, penetrations, upstands and termination heights are complete
  • Required curing, flood testing, installer declaration and protection are planned
Hold point: Do not tile or cover the membrane until the authorised waterproofing check/test is complete and defects are closed.

Evidence before release

  • Substrate and fall measurements
  • Membrane batch/installer/junction photographs
  • Test, inspection and producer/installer records required by the project

Next team: Tiler, plumber and finish installer

Open the related Workspace control →

What happens in this stage

  • Confirm framing, services, insulation, bracing, moisture, and inspection status before lining starts.
  • Check sheet type, thickness, bracing/fixing pattern, wet-area board locations, control joints, and penetrations.
  • Record concealed evidence and protect finished surfaces.

Before work starts

  • Confirm the latest issued-for-construction and consented documents for internal linings are on site, including Wall lining plan.
  • Check Plasterboard manufacturer manual, approved product data, RFIs, minor variations, and amendment status before work starts.
  • Confirm the subcontractor understands the scope, hold points, access, protection requirements, H&S controls, and quality evidence required.
  • Check the programme sequence so this stage does not start before earlier work, inspections, testing, or concealed-work photos are complete.
  • Confirm materials delivered to site match the specification, are dry/undamaged, and are stored according to manufacturer instructions.

During the work

  • Walk the work face early, mid-shift, and before close-up. Compare actual work with the consented drawings, specification, and manufacturer details.
  • Check set-out, levels, falls, clearances, penetrations, fixings, bracing, waterproofing, or protection points that will be difficult to see later.
  • Ask trades to show their own quality checks rather than only saying the work is complete.
  • Keep weather, site condition, delivery, delay, inspection, RFI, variation, and safety notes in the daily report.
  • Photograph any work before it is covered, backfilled, lined, clad, tiled, painted, or otherwise hidden.

After the work

  • Complete a close-out walk with the subcontractor and mark defects immediately while access is still available.
  • Confirm required inspection bookings, council results, producer statements, LBP Records of Work, warranties, test certificates, or installer declarations are obtained.
  • Update as-built notes where service routes, drainage, fixings, penetrations, or dimensions differ from the design.
  • Confirm the area is protected from weather, other trades, impact damage, contamination, or premature loading.
  • Update the lookahead programme and tell affected trades what is ready, what is blocked, and what must not be covered.

Common problems and step-by-step solutions

Pre-line issue
  1. 1Stop the affected internal linings activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Wrong lining product
  1. 1Stop the affected internal linings activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Bracing fixing problem
  1. 1Stop the affected internal linings activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.

Verification

Source / where to check

Use current official information and the controlled documents for the actual project.

Check structure requirements, B1/AS1, Verification Methods, structural engineer design, bracing, foundations, wind, earthquake, and consented structural drawings.

Check wet-area surfaces, ventilation, waterproofing details, and manufacturer systems against consented documents.

Manufacturer specification

Use the exact current installation manual, warranty requirements, BRANZ/Appraisal information where applicable, and product data sheet for the product on site.

Consented drawings and specifications

The issued consent drawings, stamped specifications, engineering drawings, RFIs, minor variations, and amendments control the specific project.

Manufacturer specification

Use the exact current installation manual, warranty requirements, BRANZ/Appraisal information where applicable, and product data sheet for the product on site.

Insufficient data to verify

Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.

Project-specific consented documents and professional advice override generic guidance.

Common inspections required

  • Pre-line inspection
  • Bracing lining check
  • Internal QA before stopping

Common risks

  • Bracing not fixed correctly
  • Wet framing enclosed
  • Wrong board in wet area
  • Services hidden without photos

Common mistakes

  • Lining before inspection passed
  • Wrong screw spacing for bracing
  • No access panel where needed

Required documentation

  • Latest consented drawings and specifications
  • Relevant RFIs, site instructions, amendments, minor variations, and variation approvals
  • Subcontractor scope, QA checklist, delivery dockets, product data, and installation records
  • Inspection booking/result records and photos before cover-up
  • Daily site report notes covering labour, weather, progress, delays, risks, and decisions

Photos or diagrams needed

  • Wide photo showing where internal linings is happening on the site
  • Close-up photos of critical details, fixings, laps, seals, penetrations, clearances, levels, or falls
  • Photo of product labels, batch numbers, delivery dockets, and installer marks where relevant
  • Marked-up drawing or simple diagram showing any changed location, clash, defect, or agreed remedial detail

Construction manager checklist

  1. 1Scope, drawings, specification, product data, and latest revision confirmed
  2. 2Trade briefed on hold points, tolerances to verify, evidence required, and inspection sequence
  3. 3Access, storage, protection, temporary works, and safety controls in place
  4. 4Work checked against drawings during installation, not only at completion
  5. 5Photos and records captured before work is concealed
  6. 6Defects, RFIs, delays, and variations recorded with owner and due date
  7. 7Inspection/producer statement/warranty/Record of Work requirements tracked for CCC

Questions to ask the subcontractor

  • Which drawing, detail, or manufacturer instruction are you working from?
  • What needs to be checked before this is covered or handed to the next trade?
  • What could stop you today: weather, access, materials, information, inspections, or other trades?
  • Does anything on site differ from the drawings or specification?
  • What evidence will you provide for the quality file and CCC file?

Red flags to stop work

  • Work differs from consented drawings or specification and no approved variation/RFI exists
  • A structural, weathertightness, waterproofing, drainage, fire/safety, or H1 detail is unclear
  • The trade wants to cover work before inspection, testing, or photos are complete
  • Specified materials are missing, substituted, damaged, wet, expired, or installed outside manufacturer instructions
  • A safety control is missing for excavation, heights, plant movement, electrical work, asbestos, silica, or public protection

What to record in the daily report

  • Exact location and quantity of work completed
  • Trade headcount, company names, plant used, deliveries, and material batch/product details
  • Weather, site conditions, delays, instructions received, RFIs raised, and inspections booked/passed/failed
  • Photos taken before cover-up and any defects or non-conformances found
  • Next-day lookahead, blockers, and who is responsible for each action

Use this in my project

Turn internal linings into controlled action

Open the relevant workspace register, create the project-specific record, link the controlling documents and preserve evidence. The guide does not automatically approve or verify the action.

Open workspace