Finish driveways, vehicle crossings, paths, lawns, planting, fences, and final site presentation while protecting drainage, access, and council requirements.

drivewaylandscapestormwaterhandover5 common tradesLast reviewed 11 August 2026

How to execute this stage

Micro-stage control plan

Work through each applicable step in order. A hold point means pause the dependent decision or work until the stated evidence and authorised review are complete.

3 structured steps
  1. 01Confirm driveway grades, vehicle crossing rules, stormwater flow, sub-base, reinforcement if specified, surface finish, and curing/protectionLevel 2 · External
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Confirm driveway grades, vehicle crossing rules, stormwater flow, sub-base, reinforcement if specified, surface finish, and curing/protection.

    Technical context

    Coordinate this work against Landscape plan, Driveway specification, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Poor falls. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Landscape plan is current, approved for the intended use, and available to the people doing the work.
    • Driveway specification and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the driveway/subgrade check sequence are confirmed.

    Checks

    • Check the completed work against Landscape plan and Driveway specification.
    • Check specifically for: Poor falls.
    • Avoid this known mistake: No level check at garage threshold.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed driveways and landscaping work before it is concealed.
    • Marked-up Landscape plan or a precise drawing/detail reference.
    • Driveway/subgrade check result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Driveway/subgrade check and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Poor falls
    • No level check at garage threshold
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Landscape plan
    • Driveway specification
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of driveways and landscaping. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Coordinate planting, topsoil, irrigation, fences, gates, mailboxes, and outdoor lighting.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

  2. 02Coordinate planting, topsoil, irrigation, fences, gates, mailboxes, and outdoor lightingLevel 2 · External
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Coordinate planting, topsoil, irrigation, fences, gates, mailboxes, and outdoor lighting.

    Technical context

    Coordinate this work against Civil/site levels plan, Council/vehicle crossing requirements, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Cracking. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Civil/site levels plan is current, approved for the intended use, and available to the people doing the work.
    • Council/vehicle crossing requirements and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the vehicle crossing inspection if required sequence are confirmed.

    Checks

    • Check the completed work against Civil/site levels plan and Council/vehicle crossing requirements.
    • Check specifically for: Cracking.
    • Avoid this known mistake: No protection during curing.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed driveways and landscaping work before it is concealed.
    • Marked-up Civil/site levels plan or a precise drawing/detail reference.
    • Vehicle crossing inspection if required result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Vehicle crossing inspection if required and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Cracking
    • No protection during curing
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Civil/site levels plan
    • Council/vehicle crossing requirements
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of driveways and landscaping. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Keep heavy traffic off finished surfaces until they can take load.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

  3. 03Keep heavy traffic off finished surfaces until they can take loadLevel 2 · External
    TaskCheckHold pointEvidenceRecordNext action

    Simple explanation

    Keep heavy traffic off finished surfaces until they can take load.

    Technical context

    Coordinate this work against Stormwater plan, Concrete/asphalt supplier guidance, the current consent status, and the actual site condition. Confirm interfaces before releasing dependent work.

    Why it matters: The main recorded risk is: Stormwater nuisance. A missed check can create rework, delay, hidden defects, an inspection failure, or a departure from approved project documents.

    Prerequisites

    • Stormwater plan is current, approved for the intended use, and available to the people doing the work.
    • Concrete/asphalt supplier guidance and relevant product information have been checked.
    • Access, responsibility, safety controls, preceding work and the final landscape inspection sequence are confirmed.

    Checks

    • Check the completed work against Stormwater plan and Concrete/asphalt supplier guidance.
    • Check specifically for: Stormwater nuisance.
    • Avoid this known mistake: Planting over service access points.

    Evidence to save

    • Wide, location-identifying and close-up photographs of the completed driveways and landscaping work before it is concealed.
    • Marked-up Stormwater plan or a precise drawing/detail reference.
    • Final landscape inspection result, consultant record, trade QA record or written not-applicable reason.

    Hold point

    Do not cover, backfill, load, connect, certify or release the next activity until Final landscape inspection and the required project evidence are complete or the authorised reviewer confirms what may proceed.

    Stop or escalate when

    • Stormwater nuisance
    • Planting over service access points
    • The current drawing, approval, competent reviewer or required evidence cannot be confirmed.

    Documents and records

    • Stormwater plan
    • Concrete/asphalt supplier guidance
    • Current RFI/site-instruction/change record
    • Inspection and evidence register
    Cost effect
    Rectification, reinspection, delay, damaged follow-on work, access loss and changed scope can increase the cost of driveways and landscaping. Record the cause and obtain written pricing before approving a commercial change.
    Programme effect
    This activity controls the release of dependent work. Update the lookahead programme and notify affected trades if the hold point, information, inspection or evidence is not ready.

    Next action

    Close the driveways and landscaping stage, link its evidence, resolve outstanding defects and release only the next applicable stage.

    Applicability: Apply when this work package is included in the current project scope. Confirm project-specific consent, contract, design, site and authority requirements.

    Use the current consented/issued project documents and competent site review. BuildPath does not approve work.

Trade-to-trade control

Interfaces and release gates

Use the actual consented design, specification and authorised reviewers. These controls help expose gaps; they do not approve work.

Civil drainage, building services and final ground levels

Prerequisites

  • Civil, drainage, architectural and landscape drawings use coordinated levels
  • Connection approvals, easements and authority requirements are known
  • Service crossings, retaining, access and future maintenance zones are resolved

Interface checks

  • Pipe grades, cover, bedding, separation and test points meet the approved design
  • Finished ground/paving falls do not compromise cladding, thresholds or overland flow
  • As-built survey can identify every buried service and connection
Hold point: Do not backfill or complete hard landscaping until underground work is inspected/tested, located and recorded for the as-built file.

Evidence before release

  • Open-trench photographs and test results
  • Survey/as-built information
  • Authority/council/engineer acceptance required for the actual project

Next team: External works, landscaping and close-out teams

Open the related Workspace control →

What happens in this stage

  • Confirm driveway grades, vehicle crossing rules, stormwater flow, sub-base, reinforcement if specified, surface finish, and curing/protection.
  • Coordinate planting, topsoil, irrigation, fences, gates, mailboxes, and outdoor lighting.
  • Keep heavy traffic off finished surfaces until they can take load.

Before work starts

  • Confirm the latest issued-for-construction and consented documents for driveways and landscaping are on site, including Landscape plan.
  • Check Driveway specification, approved product data, RFIs, minor variations, and amendment status before work starts.
  • Confirm the subcontractor understands the scope, hold points, access, protection requirements, H&S controls, and quality evidence required.
  • Check the programme sequence so this stage does not start before earlier work, inspections, testing, or concealed-work photos are complete.
  • Confirm materials delivered to site match the specification, are dry/undamaged, and are stored according to manufacturer instructions.

During the work

  • Walk the work face early, mid-shift, and before close-up. Compare actual work with the consented drawings, specification, and manufacturer details.
  • Check set-out, levels, falls, clearances, penetrations, fixings, bracing, waterproofing, or protection points that will be difficult to see later.
  • Ask trades to show their own quality checks rather than only saying the work is complete.
  • Keep weather, site condition, delivery, delay, inspection, RFI, variation, and safety notes in the daily report.
  • Photograph any work before it is covered, backfilled, lined, clad, tiled, painted, or otherwise hidden.

After the work

  • Complete a close-out walk with the subcontractor and mark defects immediately while access is still available.
  • Confirm required inspection bookings, council results, producer statements, LBP Records of Work, warranties, test certificates, or installer declarations are obtained.
  • Update as-built notes where service routes, drainage, fixings, penetrations, or dimensions differ from the design.
  • Confirm the area is protected from weather, other trades, impact damage, contamination, or premature loading.
  • Update the lookahead programme and tell affected trades what is ready, what is blocked, and what must not be covered.

Common problems and step-by-step solutions

Driveway ponding
  1. 1Stop the affected driveways and landscaping activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Vehicle crossing issue
  1. 1Stop the affected driveways and landscaping activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.
Landscape damage before handover
  1. 1Stop the affected driveways and landscaping activity if continuing could hide defective work, create unsafe work, or move away from the consented design.
  2. 2Photograph the condition from wide, medium, and close-up angles. Include a tape, level, datum mark, gridline, or drawing reference where useful.
  3. 3Check the latest consented architectural, structural, civil, services, and specification documents before giving an instruction.
  4. 4Ask the subcontractor to explain the cause, proposed fix, timing impact, and whether the fix changes consented work.
  5. 5Escalate to the builder/project manager, designer, engineer, council inspector, or client when the fix affects structure, weathertightness, drainage, H1, fire/safety, cost, programme, or consent.
  6. 6Record the decision, responsible person, drawing/RFI/variation reference, photos, and follow-up inspection in the daily report.

Verification

Source / where to check

Use current official information and the controlled documents for the actual project.

Check stormwater, surface water, drainage paths, and council/engineer stormwater design.

Auckland Council explains local building consent processes, CCC, related certificates, producer statements, LBP notification, and whether resource consent may also be needed.

Manufacturer specification

Use the exact current installation manual, warranty requirements, BRANZ/Appraisal information where applicable, and product data sheet for the product on site.

Consented drawings and specifications

The issued consent drawings, stamped specifications, engineering drawings, RFIs, minor variations, and amendments control the specific project.

Manufacturer specification

Use the exact current installation manual, warranty requirements, BRANZ/Appraisal information where applicable, and product data sheet for the product on site.

Insufficient data to verify

Insufficient data to verify — confirm against the current consented drawings, specifications, Auckland Council requirements, Auckland Unitary Plan, NZ Building Code, relevant NZ Standard, consultant advice, manufacturer instructions, insurance broker, insurer, lender, lawyer, accountant or project contract.

Project-specific consented documents and professional advice override generic guidance.

Common inspections required

  • Driveway/subgrade check
  • Vehicle crossing inspection if required
  • Final landscape inspection

Common risks

  • Poor falls
  • Cracking
  • Stormwater nuisance
  • Damaged services
  • Vehicle crossing non-compliance

Common mistakes

  • No level check at garage threshold
  • No protection during curing
  • Planting over service access points

Required documentation

  • Latest consented drawings and specifications
  • Relevant RFIs, site instructions, amendments, minor variations, and variation approvals
  • Subcontractor scope, QA checklist, delivery dockets, product data, and installation records
  • Inspection booking/result records and photos before cover-up
  • Daily site report notes covering labour, weather, progress, delays, risks, and decisions

Photos or diagrams needed

  • Wide photo showing where driveways and landscaping is happening on the site
  • Close-up photos of critical details, fixings, laps, seals, penetrations, clearances, levels, or falls
  • Photo of product labels, batch numbers, delivery dockets, and installer marks where relevant
  • Marked-up drawing or simple diagram showing any changed location, clash, defect, or agreed remedial detail

Construction manager checklist

  1. 1Scope, drawings, specification, product data, and latest revision confirmed
  2. 2Trade briefed on hold points, tolerances to verify, evidence required, and inspection sequence
  3. 3Access, storage, protection, temporary works, and safety controls in place
  4. 4Work checked against drawings during installation, not only at completion
  5. 5Photos and records captured before work is concealed
  6. 6Defects, RFIs, delays, and variations recorded with owner and due date
  7. 7Inspection/producer statement/warranty/Record of Work requirements tracked for CCC

Questions to ask the subcontractor

  • Which drawing, detail, or manufacturer instruction are you working from?
  • What needs to be checked before this is covered or handed to the next trade?
  • What could stop you today: weather, access, materials, information, inspections, or other trades?
  • Does anything on site differ from the drawings or specification?
  • What evidence will you provide for the quality file and CCC file?

Red flags to stop work

  • Work differs from consented drawings or specification and no approved variation/RFI exists
  • A structural, weathertightness, waterproofing, drainage, fire/safety, or H1 detail is unclear
  • The trade wants to cover work before inspection, testing, or photos are complete
  • Specified materials are missing, substituted, damaged, wet, expired, or installed outside manufacturer instructions
  • A safety control is missing for excavation, heights, plant movement, electrical work, asbestos, silica, or public protection

What to record in the daily report

  • Exact location and quantity of work completed
  • Trade headcount, company names, plant used, deliveries, and material batch/product details
  • Weather, site conditions, delays, instructions received, RFIs raised, and inspections booked/passed/failed
  • Photos taken before cover-up and any defects or non-conformances found
  • Next-day lookahead, blockers, and who is responsible for each action