BuildPath NZ logo

Legal

Easement blocks development

This can change development yield, consent pathway, purchase price, funding, construction cost, settlement timing, or legal risk. Treat it as a decision point, not background noise.

Due diligence / concept designHigheasementtitlesurveylayoutLast reviewed 11 August 2026

What it looks like

  • An easement crosses the intended building platform, driveway, services route, or subdivision layout.
  • Surveyor or lawyer says rights must be protected.

Likely causes

  • Title instruments not reviewed
  • Concept design started before survey/legal review
  • Service/access easements not understood

Immediate action

  1. 1Pause the affected decision or commitment until the issue is understood.
  2. 2Record the issue in the risk register with date, source, owner, and next action.
  3. 3Send the relevant documents to Lawyer, Surveyor, Planner and ask for written advice.
  4. 4Update feasibility, programme, budget, and decision register if cost, time, yield, consent, title, finance, or sales assumptions may change.

Step-by-step solution

  1. 1Define the problem in one sentence and identify which project decision it affects.
  2. 2Check the controlling documents: Record of Title, Easement instrument, Survey plan, Concept design.
  3. 3Ask the responsible professional to confirm whether the issue is real, minor, manageable, or project-changing.
  4. 4List the available options: redesign, renegotiate, seek consent, add cost allowance, change programme, change sales strategy, or abandon.
  5. 5Price and programme each option using the current feasibility model.
  6. 6Make a written decision with source references and approval from the developer or project owner.
  7. 7Notify affected parties such as lender, lawyer, consultants, builder, agent, buyer, or council when required.

What not to do

  • Do not rely on a seller, agent, or builder comment when a planner, lawyer, accountant, engineer, surveyor, valuer, lender, or council needs to confirm it.
  • Do not hide the issue from the feasibility just because the project looked profitable yesterday.
  • Do not waive due diligence, lodge consent, sign a contract, approve a variation, or promise settlement while the issue is unresolved.
  • Do not give legal, tax, finance, planning, engineering, or council advice to others unless a qualified professional has confirmed it.

Verification

Source / where to check

Use current official information and the controlled documents for the actual project.

Use LINZ, a lawyer, and a licensed cadastral surveyor to verify Record of Title, legal description, interests, easements, covenants, consent notices, survey plans, and boundary/title matters.

Relevant professional advice

Planner, surveyor, architect, engineer, quantity surveyor, lawyer, accountant, lender, valuer, real estate agent, and other project specialists must confirm site-specific decisions.

Project-specific consented documents and professional advice override generic guidance.

Cost impact

High if building layout, yield, services, or title structure changes.

Programme impact

Medium to high if redesign or legal work is required.

Risk level

High

Compliance and contract impact

Check whether the issue changes the resource consent pathway or conditions, building consent documents, consultant scope, sale and purchase conditions, finance terms, construction contract scope, notice requirements, variation process, or settlement obligations.

Example email / decision wording

Subject: Easement blocks development — advice and decision required. We identified this issue during due diligence / concept design. The current evidence is listed in the attached record. Please confirm the controlling requirement, available options, cost/programme implications, further information needed, and whether any consent, contract, funding, or settlement action must pause. No assumption has been approved pending written advice.

Back to development problem solver