Build Path NZResidential construction and development, made clear.

Infrastructure

Stormwater discharge problem

This can change development yield, consent pathway, purchase price, funding, construction cost, settlement timing, or legal risk. Treat it as a decision point, not background noise.

Infrastructure reviewHighstormwaterdischargedetentionsoakage

What it looks like

  • There is no clear approved discharge point, soakage is uncertain, or downstream capacity is questioned.
  • Civil costs increase for detention, retention, pumps, tanks, or outfall works.

Likely causes

  • Stormwater strategy left too late
  • Site geology unsuitable for assumed solution
  • Existing public system capacity uncertain

Immediate action

  1. 1Pause the affected decision or commitment until the issue is understood.
  2. 2Record the issue in the risk register with date, source, owner, and next action.
  3. 3Send the relevant documents to Civil engineer, Auckland Council, Geotechnical engineer and ask for written advice.
  4. 4Update feasibility, programme, budget, and decision register if cost, time, yield, consent, title, finance, or sales assumptions may change.

Step-by-step solution

  1. 1Define the problem in one sentence and identify which project decision it affects.
  2. 2Check the controlling documents: Civil stormwater report, Geotech/soakage testing, GeoMaps, Resource consent documents.
  3. 3Ask the responsible professional to confirm whether the issue is real, minor, manageable, or project-changing.
  4. 4List the available options: redesign, renegotiate, seek consent, add cost allowance, change programme, change sales strategy, or abandon.
  5. 5Price and programme each option using the current feasibility model.
  6. 6Make a written decision with source references and approval from the developer or project owner.
  7. 7Notify affected parties such as lender, lawyer, consultants, builder, agent, buyer, or council when required.

What not to do

  • Do not rely on a seller, agent, or builder comment when a planner, lawyer, accountant, engineer, surveyor, valuer, lender, or council needs to confirm it.
  • Do not hide the issue from the feasibility just because the project looked profitable yesterday.
  • Do not waive due diligence, lodge consent, sign a contract, approve a variation, or promise settlement while the issue is unresolved.
  • Do not give legal, tax, finance, planning, engineering, or council advice to others unless a qualified professional has confirmed it.

Source / Where to check

Use GeoMaps as an early desktop check for property layers, contours, flooding/overland flow information, services context, and council spatial information. Confirm critical matters with professionals and council.

Check council guidance, application requirements, RFI process, consent conditions, approved plans, engineering approvals, and monitoring requirements for site-specific development approvals.

Relevant professional advice

Planner, surveyor, architect, engineer, quantity surveyor, lawyer, accountant, lender, valuer, real estate agent, and other project specialists must confirm site-specific decisions.

Cost impact

High because stormwater design can drive earthworks, civil works, consent conditions, and site layout.

Programme impact

Medium to high due to testing, design, and approval requirements.

Risk level

High

Back to development problem solver